cutover executed: definitions live, deploy key attached, bridge paused
DEC-2026-003 deployment 2026-07-18: image with resolver + enabled definitions imported to railiance01 k3s, sync 20/20 upserted, Temporal schedules reconciled (3 Binky schedules live), cron bridge paused for the Mon-Wed verification window. Co-Authored-By: Claude Fable 5 <noreply@anthropic.com>
This commit is contained in:
parent
6ab1391b18
commit
80923a519b
1 changed files with 7 additions and 3 deletions
|
|
@ -1,8 +1,12 @@
|
|||
# Executor Cutover Runbook (BINKY-WP-0004-T06)
|
||||
|
||||
> Status: prepared 2026-07-17 — execution blocked until the gates below
|
||||
> clear. Owner of the go decision: founder (Blue lane with founder
|
||||
> notification at cutover).
|
||||
> Status: **cutover executed 2026-07-18** (DEC-2026-003 approved).
|
||||
> Definitions enabled + deployed (activity-core 73cc785, sync 20/20,
|
||||
> schedules reconciled), binky-control write deploy key attached (id 2,
|
||||
> warden lane), workstation cron line paused
|
||||
> (`#PAUSED-FOR-CUTOVER-VERIFICATION`). In verification window: three
|
||||
> clean scheduled runs expected Mon 08:23 + 09:37, Tue 08:23, Wed 08:23;
|
||||
> then the cron line is removed and the bridge marked retired.
|
||||
|
||||
## Gates (in order)
|
||||
|
||||
|
|
|
|||