# 2026-07-31 — retrospective: what CB-WP-0002 taught the loop
|
|||
|
|
|
|||
|
|
Pass: CB-WP-0002, cost accounting. Produced `tools/cb-cost.py`,
|
|||
|
|
`specs/CostAccounting.md`, ADR-0003, CB-EV-0002, and InnerLoop **v1.1**.
|
|||
|
|
|
|||
|
|
## The question the workplan asked
|
|||
|
|
|
|||
|
|
> CB-WP-0001 produced a fully specified metric that could not be computed,
|
|||
|
|
> and v1.0's "every metric names its instrument" rule was written to stop
|
|||
|
|
> that. Did it?
|
|||
|
|
|
|||
|
|
**No.** The rule was satisfied completely and the metric was still wrong.
|
|||
|
|
|
|||
|
|
`specs/CostAccounting.md` AC-1 named `cb-cost --pin fc76445` as its
|
|||
|
|
instrument — a command that did not exist when the row was written — and
|
|||
|
|
set the target to **$92.87**, computed by hand. When the tool was built one
|
|||
|
|
task later it returned **$93.32**. The hand computation carried a dedup bug
|
|||
|
|
that the tool's own positive control caught on first contact.
|
|||
|
|
|
|||
|
|
So the v1.0 rule stops "a metric with no instrument named" and does not stop
|
|||
|
|
"a metric whose target the instrument never produced". The distinction did
|
|||
|
|
not exist when the rule was written because the failure it was written for
|
|||
|
|
was the coarser one.
|
|||
|
|
|
|||
|
|
**v1.1's answer:** the instrument must exist and the target must come out of
|
|||
|
|
it. Where the tool is built later in the pass, the target is `provisional:`
|
|||
|
|
until the tool emits it, and the spec is amended to whatever it returns —
|
|||
|
|
not the reverse.
|
|||
|
|
|
|||
|
|
## The number, and its four corrections
|
|||
|
|
|
|||
|
|
The cost of CB-WP-0001 was stated four times before it was right:
|
|||
|
|
|
|||
|
|
| value | method | what was wrong |
|
|||
|
|
|---|---|---|
|
|||
|
|
| $248.46 | inherited, quoted | per-line summation (~1.9×) + single-model pricing |
|
|||
|
|
| $92.21 | re-derived, deduped, per-model | omitted the subagent tree |
|
|||
|
|
| $92.87 | + subagent at first-wins dedup | `output_tokens` is a running count |
|
|||
|
|
| **$93.32** | emitted by `cb-cost` | — |
|
|||
|
|
|
|||
|
|
Each correction was found by a different mechanism, and this is the useful
|
|||
|
|
part:
|
|||
|
|
|
|||
|
|
1. **$248.46 → $92.21** by *re-deriving instead of quoting*. Now a v1.1
|
|||
|
|
rule.
|
|||
|
|
2. **$92.21 → $92.87** by *adversarial review*, which noticed the target
|
|||
|
|
contradicted the survey's own blind-spot finding. Cost: $1.11.
|
|||
|
|
3. **$92.87 → $93.32** by the *positive control*, which fired on real data
|
|||
|
|
and refused to print a number.
|
|||
|
|
|
|||
|
|
No single mechanism found more than one. That is the argument for keeping
|
|||
|
|
all three rather than consolidating.
|
|||
|
|
|
|||
|
|
## The error class the last pass predicted, and what actually happened
|
|||
|
|
|
|||
|
|
CB-WP-0003 T10 predicted the next error would be the harness-does-nothing
|
|||
|
|
class, since four instances had already been seen. It was not — twice.
|
|||
|
|
|
|||
|
|
- The two errors in $248.46 were **trusted arithmetic over real data**. Both
|
|||
|
|
sums ran over data that genuinely existed. A positive control asserting
|
|||
|
|
"did this harness do work?" would have answered yes, correctly, and
|
|||
|
|
reported a wrong number.
|
|||
|
|
- The error in $92.87 was **a property verified on the large sample and
|
|||
|
|
assumed on the small one**. The dedup invariant was checked on the main
|
|||
|
|
transcript (206/206 groups) by the survey, and independently re-checked by
|
|||
|
|
the adversarial reviewer, who also used the main transcript. It is false
|
|||
|
|
in the 8-response subagent tree that neither examined separately.
|
|||
|
|
|
|||
|
|
The second is the one worth carrying forward, because **review structurally
|
|||
|
|
cannot catch it**: the reviewer's job is to re-derive the author's claims,
|
|||
|
|
and re-deriving on the same sample reproduces the same blind spot. Only an
|
|||
|
|
assertion running over *all* the data at execution time catches it. That is
|
|||
|
|
now a v1.1 rule (`--self-test` on every reporting tool, run before the
|
|||
|
|
number).
|
|||
|
|
|
|||
|
|
## What the pass bought, in its own units
|
|||
|
|
|
|||
|
|
The capability measures itself, which is the first time this project has
|
|||
|
|
been able to say what a pass cost while the pass was running:
|
|||
|
|
|
|||
|
|
- **CB-WP-0001 (measured retroactively):** $93.32 pinned at `fc76445`.
|
|||
|
|
88.0% cache, 11.9% output, 249:1 context re-read to text written.
|
|||
|
|
- **Adversarial review, this pass:** $1.11 — ~1% of the pass it reviewed —
|
|||
|
|
and it found three approval-blocking defects. Second consecutive pass
|
|||
|
|
where that trade was decisive. Two data points now support CB-WP-0003 T03.
|
|||
|
|
- **`/compact`, measured for the first time:** 542,991 → 19,974 tokens, a
|
|||
|
|
27× context reduction. Cost per turn fell 3.1×, from $0.457 across the
|
|||
|
|
136 turns before it to $0.149 across the 202 after.
|
|||
|
|
|
|||
|
|
That last number changes advice this project was about to give itself.
|
|||
|
|
CB-WP-0003 T04 was going to prescribe one task per session on the theory
|
|||
|
|
that long sessions are quadratic. They are **bounded**-quadratic: cost grows
|
|||
|
|
with context between compactions and resets at each one. The failure mode is
|
|||
|
|
a long *uncompacted* session, and whether a fresh session beats a compaction
|
|||
|
|
is now a measurable question rather than a matter of taste. T04 should
|
|||
|
|
measure it before prescribing.
|
|||
|
|
|
|||
|
|
## Raised, not resolved
|
|||
|
|
|
|||
|
|
- **The price sheet cannot express a time-boxed rate.** Sonnet's intro price
|
|||
|
|
is a TOML comment. Costs $0.17 today (0.19%); becomes a real error on
|
|||
|
|
**2026-08-31** when the intro rate expires and the comment and the data
|
|||
|
|
disagree in the other direction.
|
|||
|
|
- **32.5% of spend has no task**, because 19 of 33 commits carry no `T##`
|
|||
|
|
tag. Reported as its own line rather than hidden, but the underlying fix
|
|||
|
|
is commit hygiene, not tooling.
|
|||
|
|
- **Outside this repo:** the `ralph-workplan` skill instructs agents to read
|
|||
|
|
token counts from the Claude Code status bar. That is not readable from a
|
|||
|
|
tool call, so an agent asked for it estimates instead — the proximate
|
|||
|
|
cause of the hub holding 401,100 tokens for a workplan that actually
|
|||
|
|
consumed 80.9M. Flagged for the maintainer; `make cost` is the authority
|
|||
|
|
in the meantime.
|