Scope first channel extension as GLAS-WP-0003, closing GLAS-WP-0002-T04
GLAS-WP-0002 is now fully done (4/4): formalize the CLI as the first Channel extension (contract + refactor + tests + second-channel documentation), not building a second channel yet -- same generalize-from-a-real-second-example discipline as ADR-002/ADR-004. Co-Authored-By: Claude Sonnet 5 <noreply@anthropic.com>
This commit is contained in:
parent
8309c32a1b
commit
aaf8cc5f7a
3 changed files with 95 additions and 3 deletions
|
|
@ -124,9 +124,15 @@ before a second channel is attempted). Produce a scoped follow-up
|
|||
workplan (`GLAS-WP-0003` or later) rather than expanding this task
|
||||
indefinitely.
|
||||
|
||||
**Done (2026-07-26).** Scoped as
|
||||
`workplans/GLAS-WP-0003-first-channel-extension.md`: formalize the CLI
|
||||
as the first `Channel` extension (contract + refactor + tests +
|
||||
second-channel documentation), explicitly not building a second channel
|
||||
now — same discipline as ADR-002/ADR-004.
|
||||
|
||||
```task
|
||||
id: GLAS-WP-0002-T04
|
||||
status: todo
|
||||
status: done
|
||||
priority: low
|
||||
state_hub_task_id: "98d4be61-5923-4445-b1f8-5135ada13ad9"
|
||||
```
|
||||
|
|
|
|||