@ -3,7 +3,7 @@ repo: prj-forgejo-org-refactor
|
|||
repo_flavor: project
|
||||
project_status: draft
|
||||
started: "2026-08-11"
|
||||
reviewed: "2026-08-11"
|
||||
reviewed: "2026-09-28"
|
||||
---
|
||||
|
||||
# Project goal
|
||||
|
|
@ -16,10 +16,11 @@ Split the single `coulomb/` Forgejo organization into stewardship organizations
|
|||
membership expresses **discoverability and responsibility** instead of
|
||||
expressing nothing.
|
||||
|
||||
Today all 112 repositories with a Forgejo origin sit under `coulomb/`,
|
||||
At the August 11 seed review, 112 repositories with a forge origin sat under `coulomb/`,
|
||||
including `net-kingdom`, `helix-forge`, the whole `railiance-*` family, and the
|
||||
`rail-*` / `rapp-*` / `reef-*` families. An organization that contains
|
||||
everything draws no boundary and grants no useful access control.
|
||||
everything draws no useful stewardship boundary. The September 28 local scan
|
||||
finds 151 `coulomb` origins; neither count is a current server census.
|
||||
|
||||
The migration must complete **without breaking a running system**. That is the
|
||||
hard part, and it is why this is a project rather than a workplan.
|
||||
|
|
@ -29,7 +30,13 @@ hard part, and it is why this is a project rather than a workplan.
|
|||
Operator decision, 2026-08-11: seed now, execute later. The migration is only
|
||||
safe once the surrounding structure is stable enough that side-effect
|
||||
complications can be *tested for* rather than discovered in production. The
|
||||
entry gate below makes that condition checkable instead of a feeling.
|
||||
entry gate in `ORGREF-WP-0001` makes that condition checkable instead of a feeling.
|
||||
|
||||
Reviewed September 28: the family validator runs green locally; fresh deployable
|
||||
coverage, a stable full reference inventory and transfer rollback proof remain
|
||||
missing. T01/T02 can advance; T03 onward stays deferred. See the
|
||||
[readiness review](history/2026-09-28-readiness-review.md), including the circular
|
||||
dependency between the rollback prerequisite and T04.
|
||||
|
||||
## Invariants
|
||||
|
||||
|
|
@ -50,13 +57,15 @@ entry gate below makes that condition checkable instead of a feeling.
|
|||
|
||||
## Known blast radius
|
||||
|
||||
Verified 2026-08-11. This is the evidence that made the effort project-sized.
|
||||
Historical seed evidence, 2026-08-11. Reconcile current endpoints and runtime
|
||||
version before using it: forge owner docs still distinguish Gitea operation from
|
||||
a future Forgejo migration. The org split does not include that product migration.
|
||||
|
||||
| Surface | Finding | Why it hurts |
|
||||
| --- | --- | --- |
|
||||
| Git remotes | 112 repos with `coulomb/` origin | Every local clone, every CI checkout |
|
||||
| ArgoCD sources | `repoURL: https://forgejo.coulomb.social/coulomb/<repo>.git` in Application manifests | GitOps stops syncing if the path 404s |
|
||||
| **Container registry** | `repository: forgejo.coulomb.social/coulomb/core-hub` in chart values | Forgejo's package registry is **org-scoped** — a rename moves image paths for **already-running pods**, so a node reschedule or restart can fail to pull long after the rename "succeeded" |
|
||||
| **Container registry** | `repository: forgejo.coulomb.social/coulomb/core-hub` in chart values | Forgejo's package registry is **org-scoped** — changed or unavailable package paths can break a later node reschedule or restart; actual package transfer/redirect behavior remains unverified |
|
||||
| Chart metadata | `home:` / `sources:` URLs in `Chart.yaml` | Cosmetic but fleet-wide |
|
||||
| Submodules / CI configs | not yet inventoried | Unknown until the inventory task runs |
|
||||
| Hostname | `forgejo.coulomb.social` is itself coulomb-branded | Open question: does the host stay while orgs split? |
|
||||
|
|
@ -70,6 +79,8 @@ at rename time, it shows up at the next pod reschedule.
|
|||
- [ ] **G1 — Complete inventory.** Every `coulomb/` reference across git
|
||||
remotes, ArgoCD sources, chart image paths, chart metadata, submodules,
|
||||
and CI configs is enumerated by a re-runnable command, not by hand.
|
||||
Include package consumers, GitOps access policies, release/retention
|
||||
inputs and rollback references; reconcile server repos with local clones.
|
||||
- [ ] **G2 — Org taxonomy agreed.** Each repo has an assigned target org with a
|
||||
stated reason, and the criteria for assignment are written down so later
|
||||
repos can be placed without re-litigating.
|
||||
|
|
@ -79,7 +90,9 @@ at rename time, it shows up at the next pod reschedule.
|
|||
- [ ] **G4 — Rollback proven.** A repo can be moved and moved back with GitOps
|
||||
and image pulls recovering, demonstrated on a low-stakes repo first.
|
||||
- [ ] **G5 — Migration executed.** All repos sit in their target org.
|
||||
- [ ] **G6 — No stale references.** The G1 inventory command returns clean, and
|
||||
- [ ] **G6 — No stale references.** The G1 inventory command reports no unexplained
|
||||
operational references to moved paths (approved `coulomb` assignments and
|
||||
immutable historical evidence are accounted for), and
|
||||
the cluster has survived a deliberate pod reschedule on migrated images.
|
||||
- [ ] **G7 — Convention documented in a permanent home.** The org-assignment
|
||||
criteria are promoted out of this project repo, so future repos are
|
||||
|
|
|
|||
17
SCOPE.md
17
SCOPE.md
|
|
@ -44,7 +44,8 @@ by ID; it does not duplicate their tasks.
|
|||
headers, and `contribution-convention_v0.1`
|
||||
- Renaming the `forgejo.coulomb.social` host (open question, may become scope
|
||||
only if the org split forces it)
|
||||
- Any repo's internal structure or content
|
||||
- Forge product migration (Gitea/Forgejo)
|
||||
- Any repo's internal structure or content beyond coordinated migration references
|
||||
|
||||
---
|
||||
|
||||
|
|
@ -57,7 +58,9 @@ by ID; it does not duplicate their tasks.
|
|||
| `railiance-apps` | Chart image `repository:` paths and chart metadata |
|
||||
| `railiance-master` | Durable home candidate for the org-assignment convention |
|
||||
| `the-custodian` | Canon home candidate; repo-classification alignment |
|
||||
| all 112 `coulomb/` repos | Subjects of the migration |
|
||||
| Current server-backed `coulomb/` repo inventory | Subjects of the migration; 112 was the seed count |
|
||||
| `railiance-enablement` | Reusable CI/CD references and developer checkout paths |
|
||||
| Source/rapp owners | Release manifests, package consumers, workload declarations |
|
||||
|
||||
---
|
||||
|
||||
|
|
@ -71,8 +74,8 @@ by ID; it does not duplicate their tasks.
|
|||
|
||||
- Deciding which rapp a workload belongs to (different dimension)
|
||||
- Deciding which State Hub domain work belongs to (different dimension)
|
||||
- The entry gate in `GOAL.md` is not yet met — the project is deliberately
|
||||
parked until then
|
||||
- Executing T03 onward before all four entry conditions in `ORGREF-WP-0001`
|
||||
hold; read-only T01/T02 preparation remains relevant and permitted
|
||||
|
||||
---
|
||||
|
||||
|
|
@ -88,4 +91,8 @@ project's workplans, never copied.
|
|||
|
||||
- Status: **draft, deliberately deferred**
|
||||
- Seeded 2026-08-11 with the finding, blast radius, and entry gate
|
||||
- Execution begins only when the `ORGREF-WP-0001` entry gate is met
|
||||
- Reviewed 2026-09-28: local family validator green; fresh deployable coverage,
|
||||
stable full reference inventory and transfer rollback evidence still needed
|
||||
- T01/T02 preparation can proceed now; execution requires the unchanged
|
||||
`ORGREF-WP-0001` entry gate and resolution of its circular rollback dependency
|
||||
- Evidence and next sequence: [readiness review](history/2026-09-28-readiness-review.md)
|
||||
|
|
|
|||
106
history/2026-09-28-readiness-review.md
Normal file
106
history/2026-09-28-readiness-review.md
Normal file
|
|
@ -0,0 +1,106 @@
|
|||
# Readiness review — 2026-09-28
|
||||
|
||||
## Disposition
|
||||
|
||||
Keep the stewardship-org outcome and the production deferral. Read-only T01/T02
|
||||
preparation can proceed now. T03 onward cannot start: condition 1 has fresh
|
||||
positive evidence, condition 2 is unproven, and conditions 3/4 lack evidence.
|
||||
This review does not complete T01/T02 or authorize transfers, test-org creation,
|
||||
package moves, credential changes, or reschedules.
|
||||
|
||||
## Evidence and limits
|
||||
|
||||
The session read State Hub `/state/summary` and unread messages for this repo;
|
||||
the latter returned only the standing environment-orientation notice. Owner
|
||||
workplan files, rather than aggregate completion counts, support this review.
|
||||
Local checkouts were inspected; they were not fetched or changed.
|
||||
|
||||
| Entry condition | Evidence on September 28 | Assessment |
|
||||
| --- | --- | --- |
|
||||
| 1. Family validator live and green | `RMASTER-WP-0021-T05` delivered the validator on August 13. Running `python3 /home/worsch/railiance-master/tools/validate-family-declarations.py --root /home/worsch` now exits 0: 16 declarations, 0 errors, 1 informational derived-reef warning. | Satisfied for the inspected local fleet; repeat against the final migration snapshot. This is an executed validator, not evidence of a scheduled control. |
|
||||
| 2. Every live deployable maps to exactly one rapp | `RMASTER-WP-0021-T06` delivered the check; `RMASTER-WP-0025` clarified universal managed-deployable coverage. Adding `--inventory /home/worsch/railiance-platform/docs/evidence/reef-railiance-deployables.json` exits 1: 16 declarations, 36 errors, 19 warnings. That inventory was captured August 13, 22:37:46Z. | Not satisfied. These are failures against an old snapshot, not a claim that precisely 36 workloads are uncovered today. Obtain fresh complete owner inventories, then resolve missing/ambiguous ownership. |
|
||||
| 3. Stable G1 reference inventory | No project inventory command or machine-readable complete inventory exists. A bounded scan of immediate `/home/worsch` Git checkouts finds 151 origins containing `/coulomb/` or `:coulomb/`, versus the seed's 112. | Not satisfied. Local clone count is not a server repository count, may include multiple checkouts, and omits repos without local clones. It is not G1. |
|
||||
| 4. Git and package rollback demonstrated | No applicable org-transfer rollback evidence found in this project or the inspected forge workplans. Recent application rollback/retention work does not test org transfer. | Not satisfied. Requires an applicable disposable-repo evidence record, including authenticated Git and uncached package recovery. |
|
||||
|
||||
Owner revisions inspected:
|
||||
|
||||
- railiance-master: `6729627d174afaff4501ccb798c6788aa3314bbf`
|
||||
- railiance-platform: `a13fa575db507f36686eea0c42a2dea6d4b266d4`
|
||||
- railiance-forge: `e395e5e9c196fe7cea9cd2be513554e493e675ee`
|
||||
|
||||
## Progress to reuse, not rebuild
|
||||
|
||||
- `RMASTER-WP-0021-T05/T06`: schema/family validation and inventory coverage
|
||||
implementation; `RMASTER-WP-0025` (State Hub
|
||||
`09d6dfc6-0bde-5516-acaa-a6a4f0551805`): operational and tooling deployables
|
||||
also need exactly-one-rapp coverage. Non-workload actions stay outside it.
|
||||
- `RPF-WP-0009`: platform inventory producer
|
||||
`scripts/capture-reef-deployables.py` and the historical coverage snapshot.
|
||||
- `RPF-WP-0028` (`622d1208-b085-5ec2-9fb7-5e41f23e1843`): durable additive
|
||||
live-image inventory with refusal on missing/invalid exports. Its retained
|
||||
union protects old images; it is not a current deployable-ownership census.
|
||||
- `RPF-WP-0048-T03` (`6c2650a2-5da8-5999-a6e7-b22eb7c655f4`): digest-aware
|
||||
package retention deployed and verified September 27, including rollback
|
||||
protection. Org/package paths and retained aliases must join the migration
|
||||
inventory. `RPF-WP-0048-T02` remains waiting for bounded promotion admission
|
||||
and healthy observation; its September 28 record explicitly invalidates the
|
||||
previous observation interval. An existing GitOps Application is not proof
|
||||
that a migration has a usable release identity.
|
||||
|
||||
These are related owner records, not new child assignments or duplicated tasks.
|
||||
|
||||
## Corrections to the original plan
|
||||
|
||||
1. Treat 112 repositories as historical evidence. Reconcile server inventory,
|
||||
registered repositories and local clones, including archived repos and
|
||||
untracked consumers. Record exclusions and unavailable surfaces explicitly.
|
||||
2. Inventory actual forge products, versions and endpoints first. The seed uses
|
||||
`forgejo.coulomb.social`, while forge's August 22 SCOPE still describes current
|
||||
Gitea and future Forgejo migration. This discrepancy is unresolved; do not
|
||||
infer runtime identity from a hostname or conflate org transfer with a
|
||||
product/host migration.
|
||||
3. Distinguish individual repository transfer from organization rename and from
|
||||
package ownership changes. Org-scoped registry paths are a risk surface;
|
||||
automatic package movement or registry redirects are not established facts.
|
||||
4. Include GitOps AppProject source allowlists, repository credentials and access
|
||||
policy references, reusable Actions, runners/webhooks, package indexes,
|
||||
digest/tag retention inputs, release manifests, and rollback image references.
|
||||
Store reference locations and access requirements, never secret values.
|
||||
5. Keep `experimental` a proposal. Lifecycle and stewardship are different
|
||||
dimensions; default draft guidance is steward-owned experimental repositories,
|
||||
with any shared incubator requiring an explicit accountable steward.
|
||||
6. Make G6 mean zero unexplained operational references to moved paths. Valid
|
||||
`coulomb` assignments and immutable historical evidence are not stale links.
|
||||
7. The foundation plan ends at a cutover plan. Actual migration waves (G5/G6)
|
||||
and permanent convention publication (G7) require subsequent file-backed
|
||||
coordination and owner records, not an implied extension of T05.
|
||||
|
||||
## Circular gate: unresolved decision
|
||||
|
||||
Decision `e9aca79b-f167-4326-94cd-037dcea34cd2` records the conflict: condition 4
|
||||
requires the proof T04 was supposed to produce, but T04 cannot start until all
|
||||
four conditions hold. T04 is now described as revalidating accepted prior proof;
|
||||
that clarifies the unchanged rule but does not manufacture a prerequisite.
|
||||
|
||||
Recommended future amendment: once conditions 1–3 hold, allow a precisely scoped,
|
||||
isolated disposable rehearsal owned by railiance-forge, while retaining all four
|
||||
conditions before any production transfer. This requires an explicit gate
|
||||
amendment covering AGENTS.md and the workplan. Alternatively consume independently
|
||||
authorized applicable owner evidence. Neither path is assumed authorized here.
|
||||
|
||||
## Next sequence
|
||||
|
||||
1. Complete T01's repeatable inventory and reconcile its coverage; capture two
|
||||
identical normalized results with source revisions unchanged.
|
||||
2. Complete T02's steward/permissions matrix and per-repo assignments; settle
|
||||
`experimental`, retained `coulomb`, and the durable convention owner.
|
||||
3. Obtain current deployable coverage receipts from the existing owners and
|
||||
link their gap-closing work by stable ID. Repeat the family scan.
|
||||
4. Resolve the circular-gate decision and obtain valid rollback proof without
|
||||
bypassing the standing gate.
|
||||
5. Only then start T03/T04, approve evidence for G3/G4, and complete T05's staged
|
||||
cutover design. Require old/new package availability, retention protection,
|
||||
source permissions, rollback owners and abort criteria for every wave.
|
||||
6. Create follow-on migration and convention-publication workplans. Execute a
|
||||
low-stakes wave before wider transfers; prove fresh image pulls/reschedules
|
||||
and GitOps recovery, then close G5–G7 and retire the project.
|
||||
|
|
@ -9,7 +9,7 @@ flavor: implementation
|
|||
owner: codex
|
||||
topic_slug: railiance
|
||||
created: "2026-08-11"
|
||||
updated: "2026-08-19"
|
||||
updated: "2026-09-28"
|
||||
related_repos:
|
||||
- railiance-forge
|
||||
- railiance-platform
|
||||
|
|
@ -30,7 +30,7 @@ This workplan exists so the finding and its evidence are not lost, and so the
|
|||
condition for starting is written down and checkable rather than a judgement
|
||||
call made from memory months later.
|
||||
|
||||
All tasks remain `todo` (not started) while the project-wide deferral stands.
|
||||
All tasks remain `todo`: this review updates the plan, not task acceptance.
|
||||
An operator may move T01/T02 to `progress` before the full execution gate
|
||||
because they are read-only; T03 onward still requires all four gate conditions.
|
||||
|
||||
|
|
@ -52,6 +52,29 @@ because they are read-only; T03 onward still requires all four gate conditions.
|
|||
T01 and T02 below are safe to run at any time — they are read-only and they
|
||||
build the evidence the gate depends on.
|
||||
|
||||
## Readiness review — 2026-09-28
|
||||
|
||||
See [evidence, owner records and next sequence](../history/2026-09-28-readiness-review.md).
|
||||
|
||||
| Condition | Current evidence | Disposition |
|
||||
| --- | --- | --- |
|
||||
| 1 | Validator implemented in `RMASTER-WP-0021-T05`; current local scan: 16 declarations, zero errors, one warning | Green for inspected fleet; rerun before execution |
|
||||
| 2 | Coverage check exists (`RMASTER-WP-0021-T06`); universal scope clarified by `RMASTER-WP-0025`. August 13 snapshot yields 36 errors/19 warnings today | Not met; fresh complete coverage required |
|
||||
| 3 | No complete G1 command or stable paired output; bounded local count now 151 `coulomb` origins | Not met; T01 remains open |
|
||||
| 4 | No applicable Git/package transfer rollback receipt found | Not met; T03 onward remains gated |
|
||||
|
||||
**Circular prerequisite:** T04 cannot produce the first condition-4 proof while
|
||||
it is itself gated on that proof. Pending decision
|
||||
`e9aca79b-f167-4326-94cd-037dcea34cd2` proposes a separately scoped disposable
|
||||
forge-owner rehearsal after conditions 1–3, with all four conditions retained for
|
||||
production. It is a proposal, not an exception to AGENTS.md. Until the gate is
|
||||
explicitly amended, consume independently authorized applicable proof or remain
|
||||
deferred. Do not start T03/T04 to work around this dependency.
|
||||
|
||||
Reuse owner work instead of rebuilding it: `RPF-WP-0028` provides durable image
|
||||
inventory; `RPF-WP-0048-T03` provides digest/rollback retention protection.
|
||||
Neither establishes complete current rapp coverage or org-transfer recovery.
|
||||
|
||||
## Boundaries
|
||||
|
||||
This project may:
|
||||
|
|
@ -78,9 +101,22 @@ state_hub_task_id: "4964bf8f-96eb-59f0-8a50-5ecb5c7dbc8f"
|
|||
|
||||
Build the re-runnable `coulomb/` reference inventory (G1). Must cover: git
|
||||
remotes across all repos, ArgoCD `repoURL` values, chart image `repository:`
|
||||
paths, `Chart.yaml` `home:`/`sources:`, submodules, and CI configs. Output a
|
||||
paths, `Chart.yaml` `home:`/`sources:`, submodules, and CI configs. Also include AppProject source allowlists, repository access
|
||||
references, reusable Actions, runners/webhooks, package indexes, digest/tag
|
||||
retention inputs, and release/rollback image references. Output a
|
||||
machine-readable inventory under `inventory/` plus a command that can be
|
||||
re-run to verify clean at G6.
|
||||
re-run to verify clean at G6. Discover actual server product/version and all
|
||||
Git/registry endpoints; owner docs disagree with the seed's Forgejo-only naming.
|
||||
Reconcile server repository IDs with registered repos and clones; do not treat
|
||||
151 local origins as a complete server census. Inventory package ownership
|
||||
separately from linked repositories. Capture source revisions, unavailable
|
||||
surfaces, exclusions and reference owners without secret values.
|
||||
|
||||
Acceptance: two normalized inventory runs match with no intervening fleet
|
||||
changes; unresolved coverage is explicit and prevents G1 acceptance. G6 checks
|
||||
moved paths against an approved disposition list, preserving legitimate retained
|
||||
`coulomb` paths and historical records. This read-only collector/evidence belongs
|
||||
here; production fixes belong to the owning repos.
|
||||
|
||||
Known starting evidence, verified 2026-08-11: 112 repos with a `coulomb/`
|
||||
origin; `repoURL: https://forgejo.coulomb.social/coulomb/railiance-platform.git`
|
||||
|
|
@ -109,7 +145,11 @@ contribution records, which survive repo moves) and not a deployment grouping
|
|||
Open question to settle here: `experimental` is a lifecycle grouping rather than
|
||||
a stewardship one. Decide whether it is a legitimate exception or whether
|
||||
experimental work belongs in its steward's org with a different visibility or
|
||||
archival policy.
|
||||
archival policy. Draft preference: keep it with its steward unless a shared
|
||||
incubator has an explicit accountable owner. Target org names remain candidates.
|
||||
Acceptance requires every server repo's stable ID, target, steward, rationale,
|
||||
visibility/team permissions and unresolved assignment (if any); approve the
|
||||
matrix and select the permanent convention owner before declaring G2 complete.
|
||||
|
||||
```task
|
||||
id: ORGREF-WP-0001-T03
|
||||
|
|
@ -118,8 +158,11 @@ priority: high
|
|||
state_hub_task_id: "4b57ef3f-2a7c-56ff-b19d-e751b0b4685d"
|
||||
```
|
||||
|
||||
Verify Forgejo's actual rename/transfer behavior against a throwaway org (G3),
|
||||
for **both** the Git path and the package registry. Specifically: does a
|
||||
Verify the deployed forge product/version's actual behavior against a throwaway org (G3),
|
||||
for **both** the Git path and the package registry. Test repository transfer,
|
||||
organization rename and package ownership separately; do not infer that a repo
|
||||
transfer moves its packages. Include authenticated Git/CI access, private pulls,
|
||||
digests/tags and relevant package indexes. Specifically: does a
|
||||
renamed org leave a working redirect for `git clone`/`git fetch`? Does it for
|
||||
`docker pull`? For how long? Is it configurable? Do not assume from
|
||||
documentation — the container-registry path is the dangerous one because its
|
||||
|
|
@ -135,7 +178,11 @@ state_hub_task_id: "a55d95e2-6014-5d84-ba6e-b178c3901f3e"
|
|||
|
||||
Prove rollback (G4) on a low-stakes repo: move it, confirm GitOps sync and
|
||||
image pull both recover, move it back, confirm again. Produce the evidence
|
||||
record. This closes the entry gate.
|
||||
record. This revalidates the previously accepted condition-4 evidence for the selected
|
||||
migration path; it cannot bootstrap its own prerequisite under the standing gate.
|
||||
Record exact operation, product/version, old/new paths, uncached pulls, GitOps
|
||||
revision/health, retention protections, credentials scope, cleanup and recovery
|
||||
time. Unrelated application rollout rollback is not acceptable transfer proof.
|
||||
|
||||
```task
|
||||
id: ORGREF-WP-0001-T05
|
||||
|
|
@ -147,8 +194,17 @@ state_hub_task_id: "3ad6090f-5aa9-5087-a670-37d7b2ffdb7c"
|
|||
Write the migration sequencing and cutover plan from the T01–T04 evidence:
|
||||
ordering, per-stage rollback point, which references must change ahead of the
|
||||
move versus after it, and how a deliberate pod-reschedule test is used to prove
|
||||
G6 rather than assuming success.
|
||||
G6 rather than assuming success. Include release broker/admission readiness,
|
||||
AppProject/repository access updates, old/new package availability and retention
|
||||
protection for live and rollback digests. Identify owners, abort criteria and
|
||||
validation receipts for each stage. Start with a low-stakes wave; never combine
|
||||
an org split with an unplanned host or forge-product migration.
|
||||
|
||||
## Residuals
|
||||
|
||||
None yet — the project is seeded, not started.
|
||||
- Resolve pending gate decision `e9aca79b-f167-4326-94cd-037dcea34cd2`.
|
||||
- Fresh deployable coverage and gap closure remain with platform/framework and
|
||||
workload owners; link their work by stable ID rather than importing tasks.
|
||||
- T05 produces the plan only. Follow-on file-backed workplans must cover migration
|
||||
waves (G5/G6), durable convention publication (G7) and retirement evidence.
|
||||
Create those after foundation acceptance; no migration task is implied done.
|
||||
|
|
|
|||