28 lines
894 B
Markdown
28 lines
894 B
Markdown
|
|
# Milestone — foundation workplan complete
|
||
|
|
|
||
|
|
**Recorded:** 2026-08-09
|
||
|
|
**Workplan:** SHR-WP-0001 (finished)
|
||
|
|
|
||
|
|
## Delivered
|
||
|
|
|
||
|
|
| Task | Deliverable |
|
||
|
|
| --- | --- |
|
||
|
|
| T01 | `prj-` flavor canon (`project-repository-flavor_v0.1.md`) |
|
||
|
|
| T02 | SHR-INV-0001 disposition inventory (425 items) |
|
||
|
|
| T03 | Information model SHR-ARCH-IA-0001 |
|
||
|
|
| T04 | Hub-extension architecture SHR-ARCH-HUB-0001 |
|
||
|
|
| T05 | Child workplan map SHR-ARCH-MAP-0001 + child WPs |
|
||
|
|
| T06 | Baseline + retirement gates SHR-ARCH-GATES-0001 |
|
||
|
|
|
||
|
|
## Next
|
||
|
|
|
||
|
|
Implementation streams (not this foundation WP):
|
||
|
|
|
||
|
|
- RMGR-WP-0001, HUB-WP-0004 (parallel start)
|
||
|
|
- then CORE-WP-0010, STATE-WP-0079, ACTIVITY-WP-0029, OPS-WP-0003, FIN-WP-0003
|
||
|
|
- close GOAL.md gates with evidence
|
||
|
|
|
||
|
|
No residuals from foundation require new intakes: child WPs already exist;
|
||
|
|
register-CLI GOAL.md support sits on STATE-WP-0079-T03; conformance suite on
|
||
|
|
HUB-WP-0004-T05.
|