The project is retiring generation 1 with gates, inventories and evidence, while
generation 2 has already retired itself by attrition and generation 3 runs only
on a host being decommissioned. Neither fact appears in the project's records.
Observed 2026-08-20: inter-hub runs nowhere (no repo, CoulombCore endpoint dead,
railiance01 Deployment scaled 0/0) with no cutover evidence found, while
core-hub/SCOPE.md still places retiring it out of scope and plans /api/v2
compatibility against it. core-hub itself is deployed only as staging on
CoulombCore, and hub-core is a package rather than a service. The project's
capability inventory does not mention inter-hub at all, so G-DISP has been
applied to one generation only and lets gen-2 capabilities vanish unrecorded.
Six tasks, all project-shaped per SCOPE.md — decide and inventory, route
implementation to owners by identifier. The last proposes a G-GEN gate so a
generation cannot be considered superseded until its capabilities have
dispositions, its consumers are reconciled, its downstream lanes are swept, and
its successor is deployed somewhere that will still exist.
Co-Authored-By: Claude Opus 5 <noreply@anthropic.com>
Add baseline evidence (2026-08-09) and executable retirement gates mapped to
GOAL.md. Mark all foundation tasks done and workplan finished; next work is
child implementation streams.
Add architecture/child-workplan-map_v0.1.md linking streams S1–S8 to local
workplans (RMGR, HUB-0004, CORE-0010, STATE-0079, ACTIVITY-0029, OPS-0003,
FIN-0002) with dependencies and project gates.