UPC-WP-0002-T01/T02: record OH command day scheduled for Sunday 2026-08-16

Tracker moves from 'slipped, unscheduled' to a fixed date, with the Sunday
caveat recorded: OH-2026-001 has a human counterparty whose office is closed,
so the expected outcome is 4/5 closed + StB mandate awaiting reply, not 5/5.
Gate-impact table gains the expected post-day row; running order revised to put
the StB email first and the open-ended DUO backlog last.

Co-Authored-By: Claude Opus 5 <noreply@anthropic.com>
This commit is contained in:
tegwick 2026-08-16 01:24:28 +02:00
parent e0ec3df207
commit 73fb3845ee
3 changed files with 29 additions and 11 deletions

View file

@ -74,6 +74,15 @@ of repo evidence, and the explicit Orange/Red boundary (reading is Orange, any
notary-lane change is Red and must not be started on the day). All five items
now have usable prep; batch is founder-blocked, not preparation-blocked.
**Progress (2026-08-16, later):** Founder scheduled the command day for
**Sunday 2026-08-16 afternoon**. Runbook rescheduled and resequenced for a
Sunday: the Bohle-Horsmann office is closed, so OH-2026-001 loses its phone
option and becomes an *email dispatched first* (to land Monday morning) rather
than an item that closes on the day. Expected result is **4/5 closed + 001
awaiting reply**, RISK-006 to “awaiting counterparty” rather than mitigated,
with a Tue 2026-08-18 follow-up slot for call-or-fallback. OH-2026-005 was
missing from the runbook's must-do list and has been added.