Activate UPC-WP-0002 and scaffold G1 OH batch evidence.

Promote vessel close-out to active, add evidence/g1-oh-batch.md with preflight
for OH-2026-001–005, and point gate/child maps at the live command-day path.
This commit is contained in:
tegwick 2026-08-12 00:47:22 +02:00
parent 42651ff3a8
commit cd53434e18
4 changed files with 127 additions and 10 deletions

View file

@ -68,5 +68,7 @@ No change required to `SCOPE.md` participating table for this snapshot;
| ID | Status | Cluster |
| --- | --- | --- |
| UPC-WP-0001 | active → finish after T05 | Foundation (this map) |
| UPC-WP-0002 | proposed | Company vessel close-out (G1 + residual G2/G8) |
| UPC-WP-0001 | finished | Foundation (this map) |
| UPC-WP-0002 | **active** | Company vessel close-out (G1 + residual G2/G8); evidence `evidence/g1-oh-batch.md` |
| UPC-WP-0003 | proposed | Unattended dogfood + founder-load (G3G4) |
| UPC-WP-0004 | proposed | First offer + paid revenue (G5G6) |

View file

@ -5,7 +5,7 @@ repo: prj-unattended-progress-company
parent_workplan: UPC-WP-0001
repo_goal_id: "79a2b057-b765-47ad-b5d9-c1bbc49eba43"
created: "2026-08-11"
reviewed: "2026-08-11"
reviewed: "2026-08-12"
---
# Gate-to-evidence map (G1G9)
@ -18,21 +18,21 @@ Status vocabulary: `open` | `partial` | `met`.
| Gate | Title | Owning repo(s) | Known child workplans / loops | Evidence path or missing | Status | Blockers |
| --- | --- | --- | --- | --- | --- | --- |
| **G1** | Administratively clean | `binky-control` | BINKY-WP-0002 (done); OH-2026-001…005; RISK-006/007; Phase 1 checklist | `CompanyReactivationPlan.md` Phase 1; `audits/OK-Audit-v0-binky.md`; `finance/CostRunRate.md` + Qonto pull; OH queue items prepared — **Handelsregister verify, StB mandate, DUO transition still open** | **partial** | Orange: StB, DUO, Handelsregister, Qonto review; Red: bank plan changes, notary if purpose change |
| **G1** | Administratively clean | `binky-control` | BINKY-WP-0002 (done); **UPC-WP-0002 (active)**; OH-2026-001…005; RISK-006/007; Phase 1 checklist | Tracker: `evidence/g1-oh-batch.md` (0/5 closed as of 2026-08-12); runbook `binky-control/officehour/2026-08-command-day-runbook.md`; Phase 1 + audit + CostRunRate as before — **StB, DUO, HR, Qonto review, Stripe webhook still open** | **partial** | Orange: StB, DUO, Handelsregister, Qonto review, Stripe cleanup; Red: bank plan *change*, notary if purpose change |
| **G2** | Company OS active | `binky-control` | BINKY-WP-0001…0003 (done); OperatingRhythm; DecisionQueue; OfficeHourQueue; AutopilotWorkQueue; ControlLoopCatalog | `INTENT.md` v1.0 ratified DEC-2026-001; `AutonomyPolicy.md`; daily briefs through 2026-08-08; queues live | **partial** → near met | Policy “in force” is operationally true; formal checklist still marks some governance boxes open in Reactivation Plan |
| **G3** | Dogfood loop closed | `binky-control`, Railiance/`activity-core`/`llm-connect` | BINKY-WP-0003…0006 (finished); REIN-A-0003 weekly review | OK-Audit v0 dogfood; rhythm on Railiance without host coding agent; ops_run `ad0b05c4-…` weekly review proof 2026-08-08 | **partial** → strong | Need a named “S3 acceptance” evidence pack in this project; founder milestone status still ⬜ on S3 |
| **G4** | Founder load within budget | `binky-control` (measure), this project (gate evidence) | *none dedicated* | **missing** — no ≥30-day CEO time envelope log / KPI | **open** | Design + measure load; requires definition of what counts as “routine company ops” vs Red exceptions |
| **G5** | External offer published | `binky-control` (+ website/domain as needed) | BINKY-WP-0002-T04 (draft done); OfferCatalog flagship | `OfferCatalog.md` — OK Audit **drafted**, publishing Yellow-lane decision package **not closed** | **open** | Yellow decision to publish; domain/website residual (AWQ-003, Reactivation digital presence) |
| **G6** | First paid revenue | `binky-control`, finance path | BINKY-WP-0005/0007 (Qonto read path finished) | Qonto evidence of costs/credits; Binect-related credit noted — **no booked external product/service sale** | **open** | Depends on G5 + delivery; Red for contracts/payment setup if needed |
| **G7** | Repeatable path | product/service repos after first delivery | *gap* | **missing** unit economics / productized delivery after first sale | **open** | Premature until G5G6; residual to durable product repos |
| **G8** | Decision surface thin | `binky-control` | DecisionQueue hygiene; OH batching; AutonomyPolicy lanes | DecisionQueue: prepared items resolved pattern; OH: 5 prepared items batched; AWQ mostly closed/optional | **partial** | Material admin still blocked on Orange OH batch (not “nobody asked Bernd” — but not thin until G1 OH drain) |
| **G8** | Decision surface thin | `binky-control` | DecisionQueue hygiene; OH batching; AutonomyPolicy lanes; UPC-WP-0002 | OH: 5 prepared, tracked in `evidence/g1-oh-batch.md`; surface is packaged not ad-hoc | **partial** | Thinness waits on G1 OH drain (command day) |
| **G9** | Residuals owned outside project | all participating repos | work-record residual convention; AWQ residual intakes | Pattern exists (e.g. AWQ residuals with `origin_ref`); **project not complete** so gate open by definition | **open** | Close only at project retirement; enforce residual handoff as each UPC-WP finishes |
## Cluster view (for sequencing)
| Cluster | Gates | Dominant state | Coordination home |
| --- | --- | --- | --- |
| Company vessel | G1, residual G2 | G1 blocks clean vessel | **UPC-WP-0002** (drafted) |
| Company vessel | G1, residual G2 | G1 blocks clean vessel | **UPC-WP-0002** (active) |
| Unattended + load | G3, G4 | G3 strong; G4 missing | future UPC-WP-0003 |
| Revenue path | G5, G6, G7 | Offer drafted only | future UPC-WP-0004 |
| Governance close | G8, G9 | partial / endgame | continuous + retirement |

106
evidence/g1-oh-batch.md Normal file
View file

@ -0,0 +1,106 @@
---
id: UPC-EVID-G1-OH-0001
type: evidence
repo: prj-unattended-progress-company
parent_workplan: UPC-WP-0002
created: "2026-08-12"
updated: "2026-08-12"
as_of: "2026-08-12"
---
# G1 office-hour batch tracker
Authoritative OH records live in `binky-control/OfficeHourQueue.md`. This file
only tracks **status for project gates** and pointers. Do not paste secrets,
API keys, or full OH body text here.
**Command-day runbook (binky-control):**
`binky-control/officehour/2026-08-command-day-runbook.md`
(Timing was “first two weeks of August 2026”; batch still open as of this
tracker — schedule next available OH command day.)
**Closing rule:** when an OH item is `done` or deferred with residual in
binky-control, update the row here, then refresh `architecture/gate-map.md`
G1/G8 (UPC-WP-0002-T02).
## Batch status
| OH id | Title (short) | binky status | Project outcome | Closed / residual | Notes |
| --- | --- | --- | --- | --- | --- |
| OH-2026-001 | StB mandate Bohle-Horsmann (JA 2025+) | prepared | **open** | — | RISK-006; Orange |
| OH-2026-002 | DUO backlog + license transition | prepared | **open** | — | RISK-007; Orange; couples with 001 |
| OH-2026-003 | Qonto cost/access review | prepared | **open** | — | Read path done (BINKY-WP-0005); plan *change* still Red if wanted |
| OH-2026-004 | Handelsregister / address / articles | prepared | **open** | — | Weakest prep (`prepared_material: []`); public HR pull |
| OH-2026-005 | Stripe delete stale preprod webhook | prepared | **open** | — | Lowest friction; dashboard click |
**Batch summary:** 0/5 closed. G1 remains **partial**.
## Preflight (2026-08-12)
### OH-2026-001 — StB mandate
| | |
| --- | --- |
| **Lane** | Orange (call/email accountant) |
| **Prep ready?** | Yes |
| **Pointers** | `OfficeHourQueue.md`; inquiry thread `~/2binky/260706a-mandatsanfrageIngaBohle/`; JA 2024 PDF (same folder); `audits/OK-Audit-v0-binky.md`; runbook §1 |
| **Founder action** | Confirm mandate yes/no; if yes scope JA 2025 + filings + deadline notify; start DUO transfer with Weglarzy; if no choose fallback StB |
| **After** | Set OH status `done`; update RISK-006; Reactivation Plan tax checkbox; this table |
### OH-2026-002 — DUO transition
| | |
| --- | --- |
| **Lane** | Orange |
| **Prep ready?** | Partial — “Weglarzy agreed to accompany DUO transfer”; backlog size still unknown until login |
| **Pointers** | OfficeHourQueue; RISK-007; runbook §2; CostRunRate DATEV row |
| **Founder action** | Log into DUO; size backlog; upload missing receipts as feasible; confirm access continuity through StB change |
| **After** | OH `done` or residual intake for multi-week backlog; RISK-007; Reactivation bookkeeping checkbox |
### OH-2026-003 — Qonto review
| | |
| --- | --- |
| **Lane** | Orange for dashboard review; **Red** only if changing plan or new privileged access beyond existing path |
| **Prep ready?** | Strong — BINKY-WP-0005 finished; first pull 2026-07-21; CostRunRate v2; DEC-2026-004 for API path |
| **Pointers** | `finance/CostRunRate.md`; `finance/qonto-first-pull-2026-07-21.json`; `integrations/qonto-mcp.md`; runbook §3 (API provision may already be done — verify, do not re-expose keys) |
| **Founder action** | Confirm access; decide whether 70,80 €/mo plan is justified **without** requiring plan change today; only if change desired, treat as separate Red decision |
| **After** | OH `done` when review logged; residual only if plan change queued |
### OH-2026-004 — Handelsregister
| | |
| --- | --- |
| **Lane** | Orange (authority / public register) |
| **Prep ready?** | **Weak** — queue has empty `prepared_material`; runbook has steps |
| **Pointers** | runbook §4; Reactivation Plan Legal checklist; RISK residual on registry (RiskRegister) |
| **Founder action** | handelsregister.de current excerpt; verify address + GF; retrieve/file articles under `2binky/`; note Unternehmensgegenstand vs OK mission (notary only if change needed — Red) |
| **Agent follow-up (optional)** | After this OH day, improve binky `prepared_material` with file paths of downloaded excerpts (no PII dump into this project) |
| **After** | OH `done`; Reactivation legal checkboxes; this table |
### OH-2026-005 — Stripe webhook cleanup
| | |
| --- | --- |
| **Lane** | Orange-light (dashboard); can be same day or micro-session |
| **Prep ready?** | Yes — AWQ-009 diagnosis in OH body |
| **Pointers** | OfficeHourQueue OH-2026-005 steps; Autopilot AWQ-009 history |
| **Founder action** | Stripe → Developers → Webhooks → delete `api.preprod.blobr.dev`; list remaining endpoints for live pipeline |
| **After** | OH `done`; optional residual for endpoint inventory if incomplete |
## Suggested command-day order
1. **005** (510 min) — clear noise
2. **004** (register pull) — independent of StB
3. **001** then **002** — StB drives DUO
4. **003** — finance review / plan keep-or-defer
Do **not** spend the day on website/domain (AWQ-003) or offer publish (UPC-WP-0004).
## Gate impact
| When | G1 | G8 |
| --- | --- | --- |
| Now | partial (0/5) | partial (5 prepared OH) |
| After all five closed or residual-owned | reassess → `met` or `partial` with explicit residuals | reassess thinness |
| S1 mark | UPC-WP-0002-T03 Yellow package | — |

View file

@ -4,12 +4,12 @@ type: workplan
title: "Company vessel close-out (G1 + residual G2/G8)"
domain: infotech
repo: prj-unattended-progress-company
status: proposed
status: active
owner: bernd
topic_slug: infotech
repo_goal_id: "79a2b057-b765-47ad-b5d9-c1bbc49eba43"
created: "2026-08-11"
updated: "2026-08-11"
updated: "2026-08-12"
quality_dor: DoR-Ok
quality_dor_at: "2026-08-11"
quality_dor_by: "grok"
@ -48,7 +48,7 @@ actions; agents prepare packages and update maps.
```task
id: UPC-WP-0002-T01
status: todo
status: progress
priority: high
state_hub_task_id: "6da07153-7a6c-43c7-b580-7ea9f5a5195c"
```
@ -58,11 +58,16 @@ first item moves): id, date closed or deferred, outcome pointer into
`binky-control`, residual if any (`origin: residual`). Do not copy OH body
text.
**Progress (2026-08-12):** Tracker created at `evidence/g1-oh-batch.md` with
preflight for all five items (still 0/5 closed). Linked command-day runbook
`binky-control/officehour/2026-08-command-day-runbook.md`. Update rows as OH
items close in binky-control.
## Keep gate map and Reactivation checklist aligned
```task
id: UPC-WP-0002-T02
status: todo
status: progress
priority: high
state_hub_task_id: "65dfcc19-3088-427c-98d4-125b39516565"
```
@ -71,6 +76,10 @@ After each OH close (or weekly), update `architecture/gate-map.md` G1/G8 rows
and confirm `binky-control/CompanyReactivationPlan.md` Phase 1 checkboxes
match evidence. Flag any Red-lane residual explicitly.
**Progress (2026-08-12):** Gate map G1/G8 evidence column points at
`evidence/g1-oh-batch.md` and active UPC-WP-0002. Full Reactivation checklist
sync waits on first OH closes.
## Request S1 milestone update when vessel is clean enough
```task