2026-05-18 18:21:28 +02:00
---
id: RAILIANCE-WP-0002
type: workplan
title: "Establish vergabe-teilnahme as an Application on railiance01"
domain: railiance
repo: railiance-apps
status: proposed
owner: railiance
topic_slug: railiance
created: "2026-05-18"
updated: "2026-05-18"
planning_priority: high
planning_order: 2
2026-05-18 20:38:54 +02:00
state_hub_workstream_id: "94522a85-80d5-4f2c-8eb0-8d0bcb15f3b0"
2026-05-18 18:21:28 +02:00
---
# Establish vergabe-teilnahme as an Application on railiance01
## Goal
Deploy the `vergabe-teilnahme` Django application as a governed Helm release on
the production cluster node `railiance01` (`92.205.130.254` ), reachable at
`https://vergabe-teilnahme.whywhynot.de` , with its container image published
through the Railiance Gitea OCI registry and its PostgreSQL data living in the
shared cnpg cluster.
This establishes vergabe-teilnahme as the second application (after Gitea)
running on the S5 layer of the Railiance OAS Stack and exercises the freshly
enabled container registry from `RAILIANCE-WP-0001` end-to-end.
## Placement in the Railiance Tooling Set
This workplan lives in `railiance-apps` because vergabe-teilnahme is an S5
application workload. The deployment surface added by this workplan is:
- `helm/vergabe-teilnahme-values.sops.yaml` — SOPS-encrypted Helm values
(`DJANGO_SECRET_KEY` , DB DSN, etc.).
- `releases/vergabe-teilnahme/` — chart selection / overlay (Bitnami generic
chart or hand-rolled chart, decided in T05).
- `manifests/vergabe-teilnahme-ingress.yaml` — Traefik ingress + cert-manager
TLS for `vergabe-teilnahme.whywhynot.de` .
- `Makefile` targets: `vergabe-deploy` , `vergabe-status` , `vergabe-migrate` .
Cross-repo coordination required:
| Concern | Owner repo | Coordination |
|---------|------------|--------------|
| Application Helm release | `railiance-apps` | This workplan |
| Containerization (Dockerfile, entrypoint, asset build) | `vergabe-teilnahme` | This workplan opens a task in that repo |
| PostgreSQL role + database in shared cnpg cluster | `railiance-platform` | Capability request via hub |
| DNS A record for `vergabe-teilnahme.whywhynot.de` | DNS owner of `whywhynot.de` | Out-of-band, captured in T06 |
| Ingress controller / cluster routing primitives | `railiance-cluster` | Reuse — no changes expected |
| cert-manager ClusterIssuer `letsencrypt-prod` | `railiance-platform` | Reuse — no changes expected |
## Current Evidence
- `vergabe-teilnahme/CLAUDE.md` : Django 6.x · uv · Tailwind CSS v4 (Vite) ·
HTMX 2.x · Alpine.js 3.x · PostgreSQL 16+ (psycopg3). German UI.
- `vergabe-teilnahme/` currently has no `Dockerfile` . `docker-compose.dev.yml`
documents the local Postgres but isn't started when the shared
`infra-postgres-1` is up.
- `railiance-apps/Makefile` deploys Gitea via `helm/gitea-values.sops.yaml` ;
the same SOPS + Helm pattern is the template for this workplan.
- `RAILIANCE-WP-0001` confirmed `https://gitea.coulomb.social/v2/` returns
the OCI registry auth challenge. Image naming convention established:
`gitea.coulomb.social/<org>/<image>:<tag>` .
- `manifests/gitea-ingress.yaml` confirms the ingress recipe:
`ingressClassName: traefik` + annotation
`cert-manager.io/cluster-issuer: letsencrypt-prod` .
- Domain `whywhynot.de` has no prior references in any railiance repo —
DNS and a fresh Let's Encrypt cert will need to be set up.
- Live cnpg state: `gitea-db` runs in the `databases` namespace. T01
confirms whether a single shared cluster exists for app DBs or whether
one must be designated.
## Safety Contract
- Do not commit decrypted Helm values, the Django `SECRET_KEY` , DB
credentials, or any other secret material.
- Use a dedicated PostgreSQL role with privileges scoped to a single
database; never reuse the gitea role or grant superuser.
- No public exposure until cert-manager has successfully issued a TLS
certificate for `vergabe-teilnahme.whywhynot.de` .
- Do not start with `DEBUG=True` ; production settings only.
- Preserve Gitea behavior: the new ingress must not conflict with the
`gitea` ingress on the cluster's default ingress controller.
- If DB role provisioning requires changes to the shared cnpg cluster
resource limits, pause and create a `railiance-platform` task.
- If DNS for `whywhynot.de` is owned outside this operator's control,
pause T06 until DNS ownership is confirmed.
- Start fresh — no migration of data from any existing dev database in
this workplan.
## Target State
- `vergabe-teilnahme:<tag>` image is built and pushed to
`gitea.coulomb.social/coulomb/vergabe-teilnahme:<tag>` .
- A `vergabe` PostgreSQL role and `vergabe_db` database exist in the
shared cnpg cluster (single role, single DB, no cross-app grants).
- A Helm release `vergabe-teilnahme` is deployed in a dedicated
namespace with a single replica, a Service, a PVC for media (if any),
and the necessary secrets sourced from SOPS values.
- Django `migrate` and `make seed` have run successfully against the
shared cnpg database.
- `https://vergabe-teilnahme.whywhynot.de` serves the Django app behind
a valid Let's Encrypt certificate.
- Login as a superuser succeeds; the dashboard renders; static assets
are served correctly (Tailwind/Vite build pipeline integrated into the
image).
- Runbook, registry naming, DB credentials handling, and rollback steps
are documented for the next operator.
## Tasks
### T01 — Inventory the deployment substrate
```task
id: RAILIANCE-WP-0002-T01
2026-05-18 20:38:54 +02:00
status: done
2026-05-18 18:21:28 +02:00
priority: high
2026-05-18 20:38:54 +02:00
state_hub_task_id: "49aa7d85-96bd-4d97-952c-80dcfff06610"
2026-05-18 18:21:28 +02:00
```
Confirm the pre-conditions before any code is written.
Checks:
- Identify the shared cnpg cluster intended for app databases (name,
namespace, version, current databases/roles, available capacity).
- Verify `gitea.coulomb.social/v2/` still returns an OCI registry auth
challenge and that the operator has a package-capable token.
- Verify cert-manager `letsencrypt-prod` ClusterIssuer is healthy and
has successfully issued at least one production certificate recently
(`gitea-tls` is a known good example).
- Confirm DNS ownership and the change path for `whywhynot.de` — record
who owns the zone and how an A record is added.
- Confirm Traefik is the active ingress controller and note the public
IP/hostname an A record must point at.
**Done when:** the workplan records (a) the cnpg cluster to use,
(b) the operator's path to a Gitea package token, (c) the DNS change
path for `whywhynot.de` , and (d) any pre-condition gaps.
2026-05-18 20:38:54 +02:00
**Findings (2026-05-18):**
- **cnpg landscape — no shared cluster yet.** `kubectl get clusters.postgresql.cnpg.io -A` returns two
app-dedicated clusters in the `databases` namespace:
- `gitea-db` — `ghcr.io/cloudnative-pg/postgresql:18.1-system-trixie` , 1 instance, 10Gi
- `net-kingdom-pg` — `ghcr.io/cloudnative-pg/postgresql:16` , 1 instance, 10Gi
Neither was provisioned as a shared cluster. The user's earlier choice
("shared cnpg cluster, new database role") therefore requires a sub-decision —
see **Decision D-01** below.
- **Gitea registry reachable.** `curl --resolve gitea.coulomb.social:443:92.205.130.254
https://gitea.coulomb.social/v2/` returns ` HTTP 405` for ` HEAD` with a valid TLS chain
(cert: `default/gitea-tls` , ready 3d). The OCI endpoint is up; HEAD-vs-GET is expected.
- **Gitea package token — still required.** No package-capable PAT is currently held
by the operator in this session (carryover blocker from `RAILIANCE-WP-0001-T04` ).
Token must be minted via the Gitea web UI by a user with `write:package` scope before T03.
- **Public DNS for `whywhynot.de` :** A-record currently `217.160.0.212` (IONOS web hosting).
Authoritative NS = `ns1126.ui-dns.{de,biz,com,org}` (IONOS / 1& 1). The zone is
administered through the operator's IONOS web console — DNS change is a manual
out-of-band step.
- **Traefik LB public IP:** `92.205.130.254` (`kube-system/traefik` LoadBalancer service,
ports 80/443). This is the target the new A-record must point at.
- **cert-manager:** `ClusterIssuer/letsencrypt-prod` is `Ready=True` (59d). Most recent
successful issuance: `default/gitea-tls` , 3d4h ago. Several stale failing certs in
`mfa` and `sso` namespaces are unrelated to this workplan.
- **Pre-condition gaps before downstream tasks unblock:**
1. D-01 below (cnpg target cluster) — blocks T04.
2. Gitea package-capable PAT — blocks T03.
3. DNS A-record for `vergabe-teilnahme.whywhynot.de → 92.205.130.254` —
blocks T06.
**Decision D-01 — cnpg target for `vergabe_db` ** (pending; required before T04):
| Option | Pros | Cons |
|--------|------|------|
| A. New dedicated cluster `vergabe-pg` | Matches the existing one-cluster-per-app pattern; clean blast radius | Resource cost grows linearly with apps; no actual "shared" cluster emerges |
| B. Add role+db to existing `net-kingdom-pg` (PG 16) | Reuses a healthy PG 16 cluster matching vergabe-teilnahme's minimum; lowest cost | Cluster name no longer reflects its content; coupling with netkingdom domain |
| C. Add role+db to existing `gitea-db` (PG 18) | Newest cluster image; same operator | Couples gitea ops with vergabe ops; name no longer reflects content |
| D. Provision a new general-purpose cluster `apps-pg` (PG 16+) | Establishes a real shared cluster that future apps adopt | Net-new infra; needs a `railiance-platform` task to own the cluster |
Recommendation: **D** (creates the "shared cluster" the user asked for as a real
artifact rather than retrofitting an existing name). Recorded as a pending hub decision.
**Resolution (2026-05-18, bernd):** Option D. Provision a new shared cnpg cluster
`apps-pg` (PG 16, 1 instance, 10Gi initial) in namespace `databases` . cnpg `Cluster`
CRs live in `railiance-platform` per ADR-003 (confirmed: `helm/gitea-db-cluster.yaml` ).
A coordination message has been sent to `railiance-platform` requesting the cluster.
T04 below is now sequenced **after** that cluster reports healthy.
2026-05-18 18:21:28 +02:00
---
### T02 — Add Dockerfile and asset build to vergabe-teilnahme
```task
id: RAILIANCE-WP-0002-T02
2026-05-18 23:33:44 +02:00
status: done
2026-05-18 18:21:28 +02:00
priority: high
repo: vergabe-teilnahme
2026-05-18 20:38:54 +02:00
state_hub_task_id: "43ce85c4-0bdb-43c4-b0a5-81fa366800a6"
2026-05-18 18:21:28 +02:00
```
Open a companion task in the `vergabe-teilnahme` repo to add a
production-ready container image definition.
Scope:
- Multi-stage `Dockerfile` at the repo root:
- Stage 1: Node + Vite + Tailwind asset build (`npm ci` →
`npm run build` → emits to `static/dist/` ).
- Stage 2: Python image, `uv sync --frozen` , copy app and built
assets, run `manage.py collectstatic --noinput` .
- Production WSGI/ASGI server (gunicorn) listening on `:8000` .
- Whitenoise-style static asset serving (or document an alternative).
- Non-root container user, sensible `WORKDIR` , healthcheck endpoint.
- `.dockerignore` excluding `node_modules` , `media/` , `__pycache__` ,
`.venv` , `static/dist` source, etc.
- Document the build command and the chosen image tag scheme in the
vergabe-teilnahme README.
Coordination: this task crosses into `vergabe-teilnahme` . Track via a
hub task and reference the PR/commit when complete.
**Done when:** `docker build` against the vergabe-teilnahme repo produces
a runnable image that responds to a smoke request locally.
2026-05-18 23:33:44 +02:00
**Resolution (2026-05-18):** issue-facade was renamed to issue-core
upstream. Rewired vergabe-teilnahme to depend on issue-core
(`@ file:///home/worsch/issue-core` ); the three Python imports were
updated (`issue_tracker.*` → `issue_core.*` ). All 20 aufgaben tests
pass after the rewire. See vergabe-teilnahme commit `17f511f` .
Dockerfile delivered in vergabe-teilnahme repo:
- Three stages (assets / python-deps / runtime) with whitenoise
static serving and `collectstatic` at build time.
- BuildKit named context resolves the `../issue-core` path dep:
`docker build --build-context issue-core=/home/worsch/issue-core .`
- Non-root `app` user, `/health/` HEALTHCHECK, gunicorn on :8000.
- Smoke test: container reports `(healthy)` , `/health/` → 200.
**Original blocker (now resolved):** vergabe-teilnahme couldn't
`uv sync` because `pyproject.toml` referenced
2026-05-18 22:10:52 +02:00
`universal-issue-tracker @ file:///home/worsch/issue-facade` , but
2026-05-18 23:33:44 +02:00
that directory was effectively empty (only `.claude/` remained).
2026-05-18 22:10:52 +02:00
```
error: Failed to generate package metadata for
`universal-issue-tracker==0.1.0 @ directory+../issue-facade`
Caused by: /home/worsch/issue-facade does not appear to be a Python
project, as neither `pyproject.toml` nor `setup.py` are present.
```
Related candidate sources investigated:
- `/home/worsch/issue-core/` — a separate package (`issue-core` ), not
the missing `universal-issue-tracker` facade.
- `/home/worsch/markitect-main/_issue-tracking/issue-facade/` — does
not exist.
This must be resolved upstream in `vergabe-teilnahme` (or by restoring
`issue-facade` ) before T02 can produce a buildable image. Options:
1. **Restore `issue-facade`** — recover the missing source (git
reflog, backup, or recreate from `issue-core` 's public surface).
2. **Repoint** `vergabe-teilnahme` 's dep to `issue-core` directly if
that's the intended replacement, then update `uv.lock` .
3. **Vendor** a minimal stub interface in `vergabe-teilnahme/vendor/`
to unblock the container build; restore the real dep later.
Recommendation: route to whoever owns `issue-facade` (likely a
`markitect` or `personhood` domain task) and pause T02 until the dep
resolves cleanly outside Docker.
2026-05-18 18:21:28 +02:00
---
### T03 — Build and publish image to Gitea container registry
```task
id: RAILIANCE-WP-0002-T03
2026-05-19 00:27:02 +02:00
status: done
2026-05-18 18:21:28 +02:00
priority: high
2026-05-18 20:38:54 +02:00
state_hub_task_id: "d0f8db8c-fad9-4e0b-a404-9e3a04cffb05"
2026-05-18 18:21:28 +02:00
```
Push the first production image of vergabe-teilnahme through the
registry enabled in `RAILIANCE-WP-0001` .
Steps:
```bash
docker login gitea.coulomb.social
docker build -t gitea.coulomb.social/coulomb/vergabe-teilnahme:< tag > \
/home/worsch/vergabe-teilnahme
docker push gitea.coulomb.social/coulomb/vergabe-teilnahme:< tag >
```
Choose a deterministic tag scheme (`<git-sha>` recommended). Record the
exact image reference and digest used for the first deployment.
**Done when:** the image is fetchable from a disposable Kubernetes pod
on the cluster.
2026-05-19 00:27:02 +02:00
**Done (2026-05-19):**
- Pushed `gitea.coulomb.social/coulomb/vergabe-teilnahme:483a4df`
and `:latest` from the `vergabe-teilnahme:t02-smoke` build.
- Image digest: `sha256:e9bbceb35b0239c835d339295a0ae1d2d8b6d08c02a7b4e992c0ecd37de86d7a` .
- Token owner: `tegwick` (Bernd Worsch). Push namespace: `coulomb` org.
- Cluster-side pull verified via `kubectl run vt-pull-test` —
pod reached `Running` in ~7s with no `imagePullSecret` . **Package
is public by default**; T05 does not need to wire an imagePullSecret
unless the package is later made private in the Gitea web UI.
2026-05-18 18:21:28 +02:00
---
### T04 — Provision PostgreSQL role and database
```task
id: RAILIANCE-WP-0002-T04
2026-05-19 15:48:08 +02:00
status: done
2026-05-18 18:21:28 +02:00
priority: high
2026-05-18 20:38:54 +02:00
state_hub_task_id: "925ace1c-f9bf-4644-bd0b-637705d72ea6"
2026-05-18 18:21:28 +02:00
```
Create a `vergabe` PostgreSQL role and `vergabe_db` database inside the
2026-05-18 20:38:54 +02:00
new shared `apps-pg` cnpg cluster being provisioned by `railiance-platform`
(per resolved decision D-01).
Blocked on: `apps-pg` cluster reaching `Cluster in healthy state` in
2026-05-19 00:51:06 +02:00
namespace `databases` . Tracked by `railiance-platform`
**`RAILIANCE-WP-0003` ** (workstream
`665b3b9b-608a-4be4-84b6-dcb8261ff57b` ), proposed 2026-05-19 in
response to the coordination thread.
Consumer recipe (from RAILIANCE-WP-0003 T06):
1. Label the `vergabe-teilnahme` namespace
`railiance.io/postgres-client=apps-pg` so the platform's ingress
NetworkPolicy permits the connection.
2. Create a credential Secret in that namespace for the `vergabe` role.
3. Create a cnpg `Database` CR pointing at cluster `apps-pg` with
`ownerName: vergabe` and the credential Secret.
4. DSN: `postgresql://vergabe:...@apps-pg-rw.databases:5432/vergabe_db` ,
wired into the SOPS Helm values in T05.
2026-05-18 18:21:28 +02:00
Approach:
2026-05-18 20:38:54 +02:00
- Use a cnpg `Database` and `Role` resource — never an out-of-band `psql`
change without recording it.
2026-05-18 18:21:28 +02:00
- The role owns only `vergabe_db` ; no `CREATEDB` , no superuser, no grants
on other databases.
- Capture the database DSN in the SOPS values file (T05).
2026-05-18 20:38:54 +02:00
- If the cluster needs to grow (more instances, more storage, backup
inclusion), pause and add a follow-up `railiance-platform` task — do
not edit cluster-level resources from this repo.
2026-05-18 18:21:28 +02:00
**Done when:** the new role can connect to `vergabe_db` from inside the
cluster (`kubectl run --rm -it psql ...` ) and is recorded in the SOPS
values used by T05.
2026-05-19 15:48:08 +02:00
**Done (2026-05-19):**
Platform side (in `railiance-platform` , commit `017934d` ):
- `helm/apps-pg-cluster.yaml` adds `spec.managed.roles[vergabe]`
(CNPG 1.28 role lifecycle is cluster-scoped — no standalone Role CR).
- `helm/apps-pg-databases.yaml` (new) declares `Database/vergabe-db`
with `name: vergabe_db` , `owner: vergabe` .
- Bootstrap credential `databases/vergabe-app-credentials`
(`kubernetes.io/basic-auth` , `username: vergabe` , generated password).
Apps side (this workplan):
- Namespace `vergabe-teilnahme` created and labeled
`railiance.io/postgres-client=apps-pg` (per docs/apps-pg.md
opt-in contract).
- Credential Secret mirrored to
`vergabe-teilnahme/vergabe-app-credentials` so the application pod
can mount it. T05 will reference this Secret via `envFrom` or
individual `valueFrom.secretKeyRef` .
DSN for T05's SOPS Helm values:
```
postgresql://vergabe:${PASSWORD}@apps -pg-rw.databases:5432/vergabe_db
```
End-to-end verification: `kubectl exec` into a pod in the
`vergabe-teilnahme` namespace and run psql with the mirrored
credentials — returns `vergabe | vergabe_db | PostgreSQL 16.13` .
2026-05-18 18:21:28 +02:00
---
### T05 — Author Helm release for vergabe-teilnahme
```task
id: RAILIANCE-WP-0002-T05
2026-05-19 19:46:49 +02:00
status: done
2026-05-18 18:21:28 +02:00
priority: high
2026-05-18 20:38:54 +02:00
state_hub_task_id: "29ba6add-6f23-4053-acb9-9d7efa0b3881"
2026-05-18 18:21:28 +02:00
```
Add the chart selection (or bespoke chart) and SOPS-encrypted values
that turn the published image into a Kubernetes Deployment.
Deliverables:
- Decide chart approach: Bitnami `common` template, a thin in-repo
chart under `charts/vergabe-teilnahme/` , or raw manifests. Record the
rationale in the workplan log.
- `helm/vergabe-teilnahme-values.sops.yaml` containing:
- image repo + tag from T03,
- env (DJANGO_SETTINGS_MODULE=`vergabe_teilnahme.settings.prod` ,
`ALLOWED_HOSTS` , `CSRF_TRUSTED_ORIGINS` ),
- `SECRET_KEY` (generated, never committed in clear),
- DB DSN from T04,
- resource requests/limits, single replica, readiness/liveness probes
targeting the healthcheck endpoint introduced in T02.
- A dedicated namespace (`vergabe-teilnahme` ).
- Optional: PVC for media uploads if Django `MEDIA_ROOT` is needed in
v1; otherwise omit and document deferral.
- `Makefile` targets: `vergabe-deploy` , `vergabe-status` ,
`vergabe-migrate` .
**Done when:** `make vergabe-deploy` renders cleanly with `--dry-run`
and produces no plaintext secrets in the rendered manifest source.
2026-05-19 19:46:49 +02:00
**Done (2026-05-19):**
- Chart approach: thin in-repo chart `charts/vergabe-teilnahme/` rather
than SOPS-encrypted values, because the only sensitive material
(`SECRET_KEY` , `DATABASE_URL` ) lives in K8s Secrets (cnpg's
`vergabe-app-credentials` + the assembled `vergabe-teilnahme-env` ),
not in Helm values. `helm/vergabe-teilnahme-values.yaml` is therefore
plain YAML — image tag, hostnames, no secrets.
- `make vergabe-dry-run` renders 2 objects (Deployment + Service);
`grep -iE 'SECRET_KEY=|DATABASE_URL=|password'` returns empty.
- Deploy revision 2 is live: pod Running 1/1, probes green. The
HTTP-probe `httpGet.httpHeaders[Host]` is set to the public hostname
so Django's `ALLOWED_HOSTS` check passes for kube-probe (the v1
fix took one iteration — earlier attempts failed liveness with HTTP
400 because the probe sent `Host: 10.42.x.x:8000` ).
- `Makefile` targets added: `vergabe-dry-run` , `vergabe-deploy` ,
`vergabe-ingress-deploy` , `vergabe-status` , `vergabe-migrate` ,
`vergabe-seed` , `vergabe-superuser` , `vergabe-logs` .
**Lesson recorded:** the base64-generated bootstrap password contains
`=` , `+` , `/` ; embedding it raw in `DATABASE_URL` confuses
`dj-database-url` (it parses `:password@host:5432/db` and the `=`
broke the DB name into 80 characters). The Secret now stores a
URL-encoded password inside `DATABASE_URL` while the raw password
remains in `vergabe-app-credentials.password` . Future apps should
either URL-encode at Secret-build time or use individual env vars.
2026-05-18 18:21:28 +02:00
---
### T06 — DNS, ingress, and TLS for vergabe-teilnahme.whywhynot.de
```task
id: RAILIANCE-WP-0002-T06
2026-05-19 19:46:49 +02:00
status: done
2026-05-18 18:21:28 +02:00
priority: high
2026-05-18 20:38:54 +02:00
state_hub_task_id: "8e673ee6-5338-4eb5-8973-a1818b4dc7f5"
2026-05-18 18:21:28 +02:00
```
Make the application reachable behind a valid Let's Encrypt certificate.
Steps:
- Add an A record `vergabe-teilnahme.whywhynot.de` →
cluster public IP (per T01). Use the DNS change path captured in T01.
- Add `manifests/vergabe-teilnahme-ingress.yaml` modeled on
`gitea-ingress.yaml` :
- `ingressClassName: traefik` ,
- annotation `cert-manager.io/cluster-issuer: letsencrypt-prod` ,
- `tls.secretName: vergabe-teilnahme-tls` ,
- host `vergabe-teilnahme.whywhynot.de` , backend the Service from T05.
- Wait for cert-manager to issue the cert.
- Validate `https://vergabe-teilnahme.whywhynot.de/healthz` (or
equivalent) returns 200 with a trusted cert chain.
Boundary note: ingress controller and cluster networking changes
belong in `railiance-cluster` . This task only adds an `Ingress`
resource that consumes the existing controller.
**Done when:** the public hostname serves the app over HTTPS and the
certificate chain validates from outside the cluster.
2026-05-19 00:02:00 +02:00
**Progress (2026-05-18):**
- ✅ DNS A record live: `vergabe-teilnahme.whywhynot.de → 92.205.130.254`
(TTL 3600; served authoritatively by `ns1126.ui-dns.*` ).
- ✅ Traefik routing reaches the cluster: HTTP probe returns 404 — the
expected pre-state because no Ingress rule matches the host yet.
2026-05-19 19:46:49 +02:00
- ✅ `manifests/vergabe-teilnahme-ingress.yaml` committed; Traefik +
cert-manager letsencrypt-prod.
- ✅ `vergabe-teilnahme-tls` issued by cert-manager in ~35s (HTTP-01).
- ✅ External HTTPS probes: `/health/` returns 200 `{"status":"ok"}` ;
`/` redirects (302) to `/ausschreibungen/dashboard/` which renders
`<title>Übersicht</title>` (German UI); `/admin/login/` shows the
German Django admin login page. `curl` reports
`SSL verify_result: 0` (trusted chain).
2026-05-19 00:02:00 +02:00
2026-05-18 18:21:28 +02:00
---
### T07 — Initial migration, seed, and smoke test
```task
id: RAILIANCE-WP-0002-T07
2026-05-19 19:46:49 +02:00
status: in_progress
2026-05-18 18:21:28 +02:00
priority: high
2026-05-18 20:38:54 +02:00
state_hub_task_id: "be1decb5-b734-4312-b98d-20ed5299d02c"
2026-05-18 18:21:28 +02:00
```
Bring the app to a usable state in production.
Steps:
- Run `manage.py migrate` as a Kubernetes `Job` or one-shot
`kubectl exec` against the running Deployment (record which).
- Run `manage.py seed` (the `make seed` target) — vergabe-teilnahme's
idempotent seed.
- Create the first superuser via `manage.py createsuperuser` .
- Smoke checklist:
- Login at `/admin/` succeeds.
- The dashboard at `/` renders without errors.
- Static assets (Tailwind build output) are served with correct
content-type and 200 status.
- HTMX partial requests succeed on at least one page.
- A new `Ausschreibung` can be created and saved.
**Done when:** the smoke checklist passes and `kubectl logs` shows no
unexpected errors.
---
### T08 — Document handoff, runbook, and backup posture
```task
id: RAILIANCE-WP-0002-T08
status: todo
priority: medium
2026-05-18 20:38:54 +02:00
state_hub_task_id: "594d3591-b61f-40c4-850c-efaa02c859ed"
2026-05-18 18:21:28 +02:00
```
Capture everything an on-call operator needs.
Deliverables in `docs/vergabe-teilnahme.md` :
- Registry image naming and tag scheme.
- Namespace, Deployment, Service, Ingress names.
- DB DSN handling (where secrets live, how to rotate).
- Restart, rollback (`helm rollback` ), and migration commands.
- Backup posture: confirm whether the shared cnpg cluster's backup job
includes `vergabe_db` ; if not, open a `railiance-platform` follow-up.
- Pointer to the vergabe-teilnahme repo for app-level changes vs.
`railiance-apps` for Helm/ingress changes.
**Done when:** a new operator can find vergabe-teilnahme, deploy a new
image tag, and recover from a pod crash without reading this workplan.
## Completion Criteria
This workplan is complete when:
1. The vergabe-teilnahme image is published to
`gitea.coulomb.social/coulomb/vergabe-teilnahme:<tag>` .
2. A dedicated PostgreSQL role and database serve the app from the
shared cnpg cluster.
3. `helm/vergabe-teilnahme-values.sops.yaml` and the ingress manifest
are committed; `make vergabe-deploy` is the single command to deploy.
4. `https://vergabe-teilnahme.whywhynot.de` serves the app over HTTPS
with a valid Let's Encrypt cert.
5. Migrations + seed have run; the smoke checklist passes.
6. Runbook is in `docs/vergabe-teilnahme.md` .
## Notes
- This is the second application on `railiance01` (after Gitea). It
intentionally adopts the same SOPS + Helm + Traefik + cert-manager
pattern so the operator workflow stays consistent.
- v1 deliberately defers: 3-stage canary (Staged Promotion Lifecycle is
still 0/7), SSO/Keycloak integration, S3-backed media storage,
Celery + Redis workers (optional in the architecture blueprint), and
multi-replica HA. Each can become its own follow-up workplan once the
baseline runs.
- The `whywhynot.de` domain enters the Railiance stack for the first
time here. Treat the DNS path established in T01/T06 as the reference
for any future `*.whywhynot.de` workloads.