Blocked as of 2026-09-28: 0005 completes placement/custody/health delivery and 0002 contract acceptance; rail/reef or reviewed host-exception coverage.
Consume RCLK-WP-0005 infrastructure placement, custody, health and exact-source deployment receipts. Verify they satisfy the adopted 0002/0003 contract before consumer pilot. Infrastructure implementation belongs to 0005 and its owner records, not a duplicate apply here.
Blocked as of 2026-09-28: Admitted native test targets and 0005 prerequisites; measured skew/suspend/outage/recovery coverage with accepted thresholds.
Choose server-side native execution where feasible. With consumer-owner approval, test correct use and wrong-caller/owner/tenant/signature/expiry negatives, uncertain boundaries and concurrent consume. Update the consumer contract before replacing its clock. IR-WP-0004/SECRETS-WP-0010 remain independently open until their own return gates pass.
## Review operational scope and hand off later capabilities
Review availability/SLO, independent backup authorities, long offline holdover, additional languages and optional authenticated NTP/NTS infrastructure offering. Keep single-host limitations explicit. Any actionable work not delivered becomes live successor records before this plan finishes.
T04 is complete: single-host scope and deferred capabilities are decided. Remaining tasks wait on owner review or native evidence; this plan is blocked.
The [closeout review](../docs/closeout-review-2026-09-28.md) records the completed
portions, each remaining gate and its owner. No new task or workplan was opened.