The T02 slice plan marked all 167 repo-manager items receivable because
RMGR-WP-0001/0002/0003 are finished. That reads readiness off workplan
status, which is too coarse.
Verified against repo-manager/src/repo_manager/: those workplans delivered
work-record dual-run, repository observation, and scaffolding. parse/ holds
only workplan.py, and the source tree contains no reference to sbom,
repo_goal, contribution, technical_debt, or extension_point.
Only A1 (partial) and A2 are receivable -- 86 items, not 165. A3, A4 and A5
have no owner-side surface. A3 was recommended twice as the low-blast-radius
first cut; it is in fact the least ready slice in Wave A. Recommendation
withdrawn.
Critical path moves to repo-manager: a workplan there must build the
register, UI, and topic surfaces. Building them here is inadmissible under
policies/retirement-freeze.md. First executable slice is A2.