Set up practical implementation workplans (WP-0006/0007/0008)
With WP-0001/0002/0003 finished, PRD Phase 4b (hosted Trust Service) is
unblocked per SCOPE.md's own sequencing rule, and the midterm goal shifts
from framework design to practical application: governing and monetizing
repos across the coulomb Forgejo org's product lines (coulomb-loop,
net-kingdom, helix-forge, the railiance-* family).
- TREV-WP-0006: Trust Service reference implementation (PRD Phase 4b).
Eight tasks from PRD to conformance-tested hosted service, explicit that
it builds infrastructure only - no real payments or Phase tracking.
- TREV-WP-0007: Degeneration policy finalization (PRD Phase 5) and the
full canonical monetization profile catalog (remainder of Phase 3) -
pilot Phases can't responsibly launch on the placeholder pilot policy
and one-line profile defaults alone.
- TREV-WP-0008: Governance formalization (PRD Phase 7) and pilot rollout
preparation. Forces a real design decision the framework never had to
answer while single-repo-hypothetical: who is "the Licensor" across four
independent product lines. Produces draft, non-binding Phase Manifests
as worked examples for one repo per product line, and a CLA draft.
All three explicitly preserve SCOPE.md's existing "no production Phases
until legal review" guardrail rather than overriding it under pressure to
monetize real repos: WP-0008-T05 is a dedicated, human-gated go-live
decision, and no other task in any of the three workplans is permitted to
authorize a real Phase, real Commercial Entitlement sale, or real
Development Credit tracking.
Updates SCOPE.md (new Stage 0/Stage 1 maturity table, revised out-of-scope
table distinguishing "infrastructure in scope" from "going live still
gated"), PRD roadmap (Phase 4b/5/7 now active, pointing at the new
workplans), and README's active-work table accordingly.
Co-Authored-By: Claude Sonnet 5 <noreply@anthropic.com>
2026-07-29 20:27:29 +02:00
|
|
|
|
---
|
|
|
|
|
|
id: TREV-WP-0008
|
|
|
|
|
|
type: workplan
|
|
|
|
|
|
title: "Governance formalization and pilot rollout (coulomb / net-kingdom / helix-forge / railiance)"
|
|
|
|
|
|
domain: infotech
|
|
|
|
|
|
repo: target-revenue
|
|
|
|
|
|
status: active
|
|
|
|
|
|
owner: claude
|
|
|
|
|
|
topic_slug: infotech
|
|
|
|
|
|
created: "2026-07-29"
|
|
|
|
|
|
updated: "2026-07-29"
|
2026-07-29 20:28:08 +02:00
|
|
|
|
state_hub_workstream_id: "b46a30e8-8ef6-44f7-96af-a098cb4084b4"
|
Set up practical implementation workplans (WP-0006/0007/0008)
With WP-0001/0002/0003 finished, PRD Phase 4b (hosted Trust Service) is
unblocked per SCOPE.md's own sequencing rule, and the midterm goal shifts
from framework design to practical application: governing and monetizing
repos across the coulomb Forgejo org's product lines (coulomb-loop,
net-kingdom, helix-forge, the railiance-* family).
- TREV-WP-0006: Trust Service reference implementation (PRD Phase 4b).
Eight tasks from PRD to conformance-tested hosted service, explicit that
it builds infrastructure only - no real payments or Phase tracking.
- TREV-WP-0007: Degeneration policy finalization (PRD Phase 5) and the
full canonical monetization profile catalog (remainder of Phase 3) -
pilot Phases can't responsibly launch on the placeholder pilot policy
and one-line profile defaults alone.
- TREV-WP-0008: Governance formalization (PRD Phase 7) and pilot rollout
preparation. Forces a real design decision the framework never had to
answer while single-repo-hypothetical: who is "the Licensor" across four
independent product lines. Produces draft, non-binding Phase Manifests
as worked examples for one repo per product line, and a CLA draft.
All three explicitly preserve SCOPE.md's existing "no production Phases
until legal review" guardrail rather than overriding it under pressure to
monetize real repos: WP-0008-T05 is a dedicated, human-gated go-live
decision, and no other task in any of the three workplans is permitted to
authorize a real Phase, real Commercial Entitlement sale, or real
Development Credit tracking.
Updates SCOPE.md (new Stage 0/Stage 1 maturity table, revised out-of-scope
table distinguishing "infrastructure in scope" from "going live still
gated"), PRD roadmap (Phase 4b/5/7 now active, pointing at the new
workplans), and README's active-work table accordingly.
Co-Authored-By: Claude Sonnet 5 <noreply@anthropic.com>
2026-07-29 20:27:29 +02:00
|
|
|
|
---
|
|
|
|
|
|
|
|
|
|
|
|
# Governance formalization and pilot rollout
|
|
|
|
|
|
|
|
|
|
|
|
The midterm goal: govern and monetize the evolution of repos across the
|
|
|
|
|
|
`coulomb` Forgejo org's product lines — `coulomb-loop`, `net-kingdom`,
|
|
|
|
|
|
`helix-forge`, and the `railiance-*` family (`railiance-apps`,
|
|
|
|
|
|
`railiance-bootstrap`, `railiance-cluster`, `railiance-enablement`,
|
|
|
|
|
|
`railiance-fabric`, `railiance-forge`, `railiance-hosts`, `railiance-infra`,
|
|
|
|
|
|
`railiance-master`, `railiance-platform`). This workplan formalizes the
|
|
|
|
|
|
governance the framework has been designed around but never actually
|
|
|
|
|
|
written down, and prepares (but does not itself execute) the first real
|
|
|
|
|
|
Phase declarations.
|
|
|
|
|
|
|
|
|
|
|
|
**Hard gate, stated up front:** `SCOPE.md` §3 lists "governing third-party
|
|
|
|
|
|
product Phases in production" as out of scope "after legal + Stage 0
|
|
|
|
|
|
package ready" — i.e., not yet. This workplan's rollout tasks (T03–T04)
|
|
|
|
|
|
produce **draft, non-binding** Phase Manifests as worked examples, exactly
|
|
|
|
|
|
like `examples/phase-001/` already is. **No real Commercial Entitlement may
|
|
|
|
|
|
be sold, no real Development Credit tracked, and no repo's actual License
|
|
|
|
|
|
header changed to TRSL, until T05 (the go-live gate) is explicitly
|
|
|
|
|
|
accepted** — after TRSL/CUA specialist legal review (`workplans/TREV-WP-0004-global-jurisdiction-research.md` /
|
|
|
|
|
|
`workplans/TREV-WP-0005-enforcement-network-research.md` T10 syntheses
|
|
|
|
|
|
feed this) and T01 (Licensor governance) are both resolved. Moving fast on
|
|
|
|
|
|
T01–T04 must not create pressure to skip T05.
|
|
|
|
|
|
|
|
|
|
|
|
## Governance document: TRSL-Governance.md
|
|
|
|
|
|
|
|
|
|
|
|
```task
|
|
|
|
|
|
id: TREV-WP-0008-T01
|
|
|
|
|
|
status: todo
|
|
|
|
|
|
priority: high
|
2026-07-29 20:28:08 +02:00
|
|
|
|
state_hub_task_id: "bae630d7-907b-4eb4-bad4-d72803ccbd33"
|
Set up practical implementation workplans (WP-0006/0007/0008)
With WP-0001/0002/0003 finished, PRD Phase 4b (hosted Trust Service) is
unblocked per SCOPE.md's own sequencing rule, and the midterm goal shifts
from framework design to practical application: governing and monetizing
repos across the coulomb Forgejo org's product lines (coulomb-loop,
net-kingdom, helix-forge, the railiance-* family).
- TREV-WP-0006: Trust Service reference implementation (PRD Phase 4b).
Eight tasks from PRD to conformance-tested hosted service, explicit that
it builds infrastructure only - no real payments or Phase tracking.
- TREV-WP-0007: Degeneration policy finalization (PRD Phase 5) and the
full canonical monetization profile catalog (remainder of Phase 3) -
pilot Phases can't responsibly launch on the placeholder pilot policy
and one-line profile defaults alone.
- TREV-WP-0008: Governance formalization (PRD Phase 7) and pilot rollout
preparation. Forces a real design decision the framework never had to
answer while single-repo-hypothetical: who is "the Licensor" across four
independent product lines. Produces draft, non-binding Phase Manifests
as worked examples for one repo per product line, and a CLA draft.
All three explicitly preserve SCOPE.md's existing "no production Phases
until legal review" guardrail rather than overriding it under pressure to
monetize real repos: WP-0008-T05 is a dedicated, human-gated go-live
decision, and no other task in any of the three workplans is permitted to
authorize a real Phase, real Commercial Entitlement sale, or real
Development Credit tracking.
Updates SCOPE.md (new Stage 0/Stage 1 maturity table, revised out-of-scope
table distinguishing "infrastructure in scope" from "going live still
gated"), PRD roadmap (Phase 4b/5/7 now active, pointing at the new
workplans), and README's active-work table accordingly.
Co-Authored-By: Claude Sonnet 5 <noreply@anthropic.com>
2026-07-29 20:27:29 +02:00
|
|
|
|
```
|
|
|
|
|
|
|
|
|
|
|
|
Produce `specs/TRSL-Governance.md`, per `spec/TargetRevenueLicenseConcept.md`
|
|
|
|
|
|
§20 (complexity budget, versioning, extension governance, operator
|
|
|
|
|
|
governance). Must resolve one question this rollout makes concretely
|
|
|
|
|
|
unavoidable for the first time: **who is "the Licensor"** across four
|
|
|
|
|
|
different product lines under one Forgejo org — a single shared Licensor
|
|
|
|
|
|
entity for all four (simplest, but conflates genuinely different products'
|
|
|
|
|
|
commercial decisions), or a per-product-line Licensor (each of
|
|
|
|
|
|
`coulomb-loop`, `net-kingdom`, `helix-forge`, `railiance` declaring its own
|
|
|
|
|
|
Phases independently under a shared TRSL/CUA template)? This was never
|
|
|
|
|
|
forced while the framework was single-repo-hypothetical; it is now.
|
|
|
|
|
|
Also define: change process for the License/CUA templates themselves once
|
|
|
|
|
|
multiple product lines depend on them, extension canonicalization review
|
|
|
|
|
|
(coordinate with `workplans/TREV-WP-0007-degeneration-policy-and-canonical-profiles.md`
|
|
|
|
|
|
T04's narrower checklist), and dispute/conflict-of-interest handling per
|
|
|
|
|
|
concept §20.3–§20.4.
|
|
|
|
|
|
|
|
|
|
|
|
## Repo inventory and Phase-candidate survey
|
|
|
|
|
|
|
|
|
|
|
|
```task
|
|
|
|
|
|
id: TREV-WP-0008-T02
|
|
|
|
|
|
status: todo
|
|
|
|
|
|
priority: high
|
2026-07-29 20:28:08 +02:00
|
|
|
|
state_hub_task_id: "4f4f4922-4bc6-4ff9-a408-b836287186db"
|
Set up practical implementation workplans (WP-0006/0007/0008)
With WP-0001/0002/0003 finished, PRD Phase 4b (hosted Trust Service) is
unblocked per SCOPE.md's own sequencing rule, and the midterm goal shifts
from framework design to practical application: governing and monetizing
repos across the coulomb Forgejo org's product lines (coulomb-loop,
net-kingdom, helix-forge, the railiance-* family).
- TREV-WP-0006: Trust Service reference implementation (PRD Phase 4b).
Eight tasks from PRD to conformance-tested hosted service, explicit that
it builds infrastructure only - no real payments or Phase tracking.
- TREV-WP-0007: Degeneration policy finalization (PRD Phase 5) and the
full canonical monetization profile catalog (remainder of Phase 3) -
pilot Phases can't responsibly launch on the placeholder pilot policy
and one-line profile defaults alone.
- TREV-WP-0008: Governance formalization (PRD Phase 7) and pilot rollout
preparation. Forces a real design decision the framework never had to
answer while single-repo-hypothetical: who is "the Licensor" across four
independent product lines. Produces draft, non-binding Phase Manifests
as worked examples for one repo per product line, and a CLA draft.
All three explicitly preserve SCOPE.md's existing "no production Phases
until legal review" guardrail rather than overriding it under pressure to
monetize real repos: WP-0008-T05 is a dedicated, human-gated go-live
decision, and no other task in any of the three workplans is permitted to
authorize a real Phase, real Commercial Entitlement sale, or real
Development Credit tracking.
Updates SCOPE.md (new Stage 0/Stage 1 maturity table, revised out-of-scope
table distinguishing "infrastructure in scope" from "going live still
gated"), PRD roadmap (Phase 4b/5/7 now active, pointing at the new
workplans), and README's active-work table accordingly.
Co-Authored-By: Claude Sonnet 5 <noreply@anthropic.com>
2026-07-29 20:27:29 +02:00
|
|
|
|
```
|
|
|
|
|
|
|
|
|
|
|
|
For each of `coulomb-loop`, `net-kingdom`, `helix-forge`, and the
|
|
|
|
|
|
`railiance-*` family: survey current repo goals and status (via the state
|
|
|
|
|
|
hub's `get_domain_summary`/`list_domain_repos`/repo-goal tools, or direct
|
|
|
|
|
|
repo inspection where hub data is thin) to identify one plausible first
|
|
|
|
|
|
Milestone Release candidate per product line — a bounded, recently- or
|
|
|
|
|
|
soon-to-be-completed piece of work with a defensible Target Multiple
|
|
|
|
|
|
classification (`specs/TargetRevenueFrameworkCore.md` §1.4), not an
|
|
|
|
|
|
arbitrary pick. Document why each candidate was chosen and what was
|
|
|
|
|
|
passed over.
|
|
|
|
|
|
|
|
|
|
|
|
## Draft pilot Phase Manifests (non-binding worked examples)
|
|
|
|
|
|
|
|
|
|
|
|
```task
|
|
|
|
|
|
id: TREV-WP-0008-T03
|
|
|
|
|
|
status: todo
|
|
|
|
|
|
priority: high
|
2026-07-29 20:28:08 +02:00
|
|
|
|
state_hub_task_id: "942943ae-14a2-4f23-888e-6084aa9c6024"
|
Set up practical implementation workplans (WP-0006/0007/0008)
With WP-0001/0002/0003 finished, PRD Phase 4b (hosted Trust Service) is
unblocked per SCOPE.md's own sequencing rule, and the midterm goal shifts
from framework design to practical application: governing and monetizing
repos across the coulomb Forgejo org's product lines (coulomb-loop,
net-kingdom, helix-forge, the railiance-* family).
- TREV-WP-0006: Trust Service reference implementation (PRD Phase 4b).
Eight tasks from PRD to conformance-tested hosted service, explicit that
it builds infrastructure only - no real payments or Phase tracking.
- TREV-WP-0007: Degeneration policy finalization (PRD Phase 5) and the
full canonical monetization profile catalog (remainder of Phase 3) -
pilot Phases can't responsibly launch on the placeholder pilot policy
and one-line profile defaults alone.
- TREV-WP-0008: Governance formalization (PRD Phase 7) and pilot rollout
preparation. Forces a real design decision the framework never had to
answer while single-repo-hypothetical: who is "the Licensor" across four
independent product lines. Produces draft, non-binding Phase Manifests
as worked examples for one repo per product line, and a CLA draft.
All three explicitly preserve SCOPE.md's existing "no production Phases
until legal review" guardrail rather than overriding it under pressure to
monetize real repos: WP-0008-T05 is a dedicated, human-gated go-live
decision, and no other task in any of the three workplans is permitted to
authorize a real Phase, real Commercial Entitlement sale, or real
Development Credit tracking.
Updates SCOPE.md (new Stage 0/Stage 1 maturity table, revised out-of-scope
table distinguishing "infrastructure in scope" from "going live still
gated"), PRD roadmap (Phase 4b/5/7 now active, pointing at the new
workplans), and README's active-work table accordingly.
Co-Authored-By: Claude Sonnet 5 <noreply@anthropic.com>
2026-07-29 20:27:29 +02:00
|
|
|
|
```
|
|
|
|
|
|
|
|
|
|
|
|
Using T02's candidates, draft one Phase Manifest per product line
|
|
|
|
|
|
following `specs/PhaseManifestSpecification.md` and
|
|
|
|
|
|
`schemas/phase_manifest.schema.json` exactly — structurally valid,
|
|
|
|
|
|
conformance-tested the same way `examples/phase-001/` is, but explicitly
|
|
|
|
|
|
marked **draft / not yet declared** (no real Commercial Use restriction
|
|
|
|
|
|
takes effect from these). Choose an applicable Monetization Extension per
|
|
|
|
|
|
Phase from `workplans/TREV-WP-0007-degeneration-policy-and-canonical-profiles.md`
|
|
|
|
|
|
T03's catalog.
|
|
|
|
|
|
|
|
|
|
|
|
## Contributor rights instrument (CLA)
|
|
|
|
|
|
|
|
|
|
|
|
```task
|
|
|
|
|
|
id: TREV-WP-0008-T04
|
|
|
|
|
|
status: todo
|
|
|
|
|
|
priority: medium
|
2026-07-29 20:28:08 +02:00
|
|
|
|
state_hub_task_id: "666a800b-96a7-4664-9448-24af989b57c5"
|
Set up practical implementation workplans (WP-0006/0007/0008)
With WP-0001/0002/0003 finished, PRD Phase 4b (hosted Trust Service) is
unblocked per SCOPE.md's own sequencing rule, and the midterm goal shifts
from framework design to practical application: governing and monetizing
repos across the coulomb Forgejo org's product lines (coulomb-loop,
net-kingdom, helix-forge, the railiance-* family).
- TREV-WP-0006: Trust Service reference implementation (PRD Phase 4b).
Eight tasks from PRD to conformance-tested hosted service, explicit that
it builds infrastructure only - no real payments or Phase tracking.
- TREV-WP-0007: Degeneration policy finalization (PRD Phase 5) and the
full canonical monetization profile catalog (remainder of Phase 3) -
pilot Phases can't responsibly launch on the placeholder pilot policy
and one-line profile defaults alone.
- TREV-WP-0008: Governance formalization (PRD Phase 7) and pilot rollout
preparation. Forces a real design decision the framework never had to
answer while single-repo-hypothetical: who is "the Licensor" across four
independent product lines. Produces draft, non-binding Phase Manifests
as worked examples for one repo per product line, and a CLA draft.
All three explicitly preserve SCOPE.md's existing "no production Phases
until legal review" guardrail rather than overriding it under pressure to
monetize real repos: WP-0008-T05 is a dedicated, human-gated go-live
decision, and no other task in any of the three workplans is permitted to
authorize a real Phase, real Commercial Entitlement sale, or real
Development Credit tracking.
Updates SCOPE.md (new Stage 0/Stage 1 maturity table, revised out-of-scope
table distinguishing "infrastructure in scope" from "going live still
gated"), PRD roadmap (Phase 4b/5/7 now active, pointing at the new
workplans), and README's active-work table accordingly.
Co-Authored-By: Claude Sonnet 5 <noreply@anthropic.com>
2026-07-29 20:27:29 +02:00
|
|
|
|
```
|
|
|
|
|
|
|
|
|
|
|
|
`CONTRIBUTING.md` currently blocks external contributions into any
|
|
|
|
|
|
governed Milestone Release until a contributor-rights instrument exists
|
|
|
|
|
|
(per `history/260729-TRSL-ContributorRights-Research.md`). If any pilot
|
|
|
|
|
|
candidate from T02 has, or expects, external contributors before its
|
|
|
|
|
|
Conversion Event, this is now practically blocking, not theoretical.
|
|
|
|
|
|
Produce `specs/TRSL-ContributorLicenseAgreement-Draft.md`: a CLA scoped
|
|
|
|
|
|
narrowly to the current Phase's TRSL terms plus its already-declared
|
|
|
|
|
|
Future License, per the T04 research's recommendation. Same preliminary-
|
|
|
|
|
|
candidate treatment as the License/CUA V1C1 documents (status banner,
|
|
|
|
|
|
Appendix A-style candidate notes) — this is a new legal document, not
|
|
|
|
|
|
exempt from that pattern.
|
|
|
|
|
|
|
|
|
|
|
|
## Go-live gate (human decision)
|
|
|
|
|
|
|
|
|
|
|
|
```task
|
|
|
|
|
|
id: TREV-WP-0008-T05
|
|
|
|
|
|
status: todo
|
|
|
|
|
|
priority: high
|
|
|
|
|
|
human_accept_required: true
|
2026-07-29 20:28:08 +02:00
|
|
|
|
state_hub_task_id: "af688189-8151-4170-925f-b3c4806a68ed"
|
Set up practical implementation workplans (WP-0006/0007/0008)
With WP-0001/0002/0003 finished, PRD Phase 4b (hosted Trust Service) is
unblocked per SCOPE.md's own sequencing rule, and the midterm goal shifts
from framework design to practical application: governing and monetizing
repos across the coulomb Forgejo org's product lines (coulomb-loop,
net-kingdom, helix-forge, the railiance-* family).
- TREV-WP-0006: Trust Service reference implementation (PRD Phase 4b).
Eight tasks from PRD to conformance-tested hosted service, explicit that
it builds infrastructure only - no real payments or Phase tracking.
- TREV-WP-0007: Degeneration policy finalization (PRD Phase 5) and the
full canonical monetization profile catalog (remainder of Phase 3) -
pilot Phases can't responsibly launch on the placeholder pilot policy
and one-line profile defaults alone.
- TREV-WP-0008: Governance formalization (PRD Phase 7) and pilot rollout
preparation. Forces a real design decision the framework never had to
answer while single-repo-hypothetical: who is "the Licensor" across four
independent product lines. Produces draft, non-binding Phase Manifests
as worked examples for one repo per product line, and a CLA draft.
All three explicitly preserve SCOPE.md's existing "no production Phases
until legal review" guardrail rather than overriding it under pressure to
monetize real repos: WP-0008-T05 is a dedicated, human-gated go-live
decision, and no other task in any of the three workplans is permitted to
authorize a real Phase, real Commercial Entitlement sale, or real
Development Credit tracking.
Updates SCOPE.md (new Stage 0/Stage 1 maturity table, revised out-of-scope
table distinguishing "infrastructure in scope" from "going live still
gated"), PRD roadmap (Phase 4b/5/7 now active, pointing at the new
workplans), and README's active-work table accordingly.
Co-Authored-By: Claude Sonnet 5 <noreply@anthropic.com>
2026-07-29 20:27:29 +02:00
|
|
|
|
```
|
|
|
|
|
|
|
|
|
|
|
|
**Do not mark this task done to authorize real Phase declarations.** It
|
|
|
|
|
|
exists to make the go-live decision a single, explicit, recorded moment
|
|
|
|
|
|
rather than something that happens by accretion once enough pilot
|
|
|
|
|
|
infrastructure exists. Before acceptance, confirm:
|
|
|
|
|
|
|
|
|
|
|
|
- `workplans/TREV-WP-0004-global-jurisdiction-research.md` T10 and
|
|
|
|
|
|
`workplans/TREV-WP-0005-enforcement-network-research.md` T10 syntheses
|
2026-07-29 20:46:49 +02:00
|
|
|
|
are complete — **done** (both finished 2026-07-29; see
|
|
|
|
|
|
`history/260729-TRSL-Jurisdiction-Synthesis.md` and
|
|
|
|
|
|
`history/260729-TREN-Synthesis.md`);
|
Set up practical implementation workplans (WP-0006/0007/0008)
With WP-0001/0002/0003 finished, PRD Phase 4b (hosted Trust Service) is
unblocked per SCOPE.md's own sequencing rule, and the midterm goal shifts
from framework design to practical application: governing and monetizing
repos across the coulomb Forgejo org's product lines (coulomb-loop,
net-kingdom, helix-forge, the railiance-* family).
- TREV-WP-0006: Trust Service reference implementation (PRD Phase 4b).
Eight tasks from PRD to conformance-tested hosted service, explicit that
it builds infrastructure only - no real payments or Phase tracking.
- TREV-WP-0007: Degeneration policy finalization (PRD Phase 5) and the
full canonical monetization profile catalog (remainder of Phase 3) -
pilot Phases can't responsibly launch on the placeholder pilot policy
and one-line profile defaults alone.
- TREV-WP-0008: Governance formalization (PRD Phase 7) and pilot rollout
preparation. Forces a real design decision the framework never had to
answer while single-repo-hypothetical: who is "the Licensor" across four
independent product lines. Produces draft, non-binding Phase Manifests
as worked examples for one repo per product line, and a CLA draft.
All three explicitly preserve SCOPE.md's existing "no production Phases
until legal review" guardrail rather than overriding it under pressure to
monetize real repos: WP-0008-T05 is a dedicated, human-gated go-live
decision, and no other task in any of the three workplans is permitted to
authorize a real Phase, real Commercial Entitlement sale, or real
Development Credit tracking.
Updates SCOPE.md (new Stage 0/Stage 1 maturity table, revised out-of-scope
table distinguishing "infrastructure in scope" from "going live still
gated"), PRD roadmap (Phase 4b/5/7 now active, pointing at the new
workplans), and README's active-work table accordingly.
Co-Authored-By: Claude Sonnet 5 <noreply@anthropic.com>
2026-07-29 20:27:29 +02:00
|
|
|
|
- specialist legal review of `specs/TargetRevenueSourceLicense-V1C1.md`
|
|
|
|
|
|
and `specs/TargetRevenueCommercialUseAgreement-V1C1.md` (condition 1 in
|
|
|
|
|
|
each document's status banner) has occurred, or is explicitly waived for
|
2026-07-29 20:46:49 +02:00
|
|
|
|
a defined pilot scope — **the maintainer has already waived full review
|
|
|
|
|
|
until out of beta** (`SCOPE.md` §1, 2026-07-29); T05 acceptance still
|
|
|
|
|
|
requires confirming the specific pilot scope this waiver covers and that
|
|
|
|
|
|
the alpha/beta working defaults adopted by the two syntheses above
|
|
|
|
|
|
(governing law/arbitration, liability cap, data protection, Enforcement
|
|
|
|
|
|
Network fee mechanics) are acceptable for that scope — this is not
|
|
|
|
|
|
automatically satisfied by the waiver existing in the abstract;
|
Set up practical implementation workplans (WP-0006/0007/0008)
With WP-0001/0002/0003 finished, PRD Phase 4b (hosted Trust Service) is
unblocked per SCOPE.md's own sequencing rule, and the midterm goal shifts
from framework design to practical application: governing and monetizing
repos across the coulomb Forgejo org's product lines (coulomb-loop,
net-kingdom, helix-forge, the railiance-* family).
- TREV-WP-0006: Trust Service reference implementation (PRD Phase 4b).
Eight tasks from PRD to conformance-tested hosted service, explicit that
it builds infrastructure only - no real payments or Phase tracking.
- TREV-WP-0007: Degeneration policy finalization (PRD Phase 5) and the
full canonical monetization profile catalog (remainder of Phase 3) -
pilot Phases can't responsibly launch on the placeholder pilot policy
and one-line profile defaults alone.
- TREV-WP-0008: Governance formalization (PRD Phase 7) and pilot rollout
preparation. Forces a real design decision the framework never had to
answer while single-repo-hypothetical: who is "the Licensor" across four
independent product lines. Produces draft, non-binding Phase Manifests
as worked examples for one repo per product line, and a CLA draft.
All three explicitly preserve SCOPE.md's existing "no production Phases
until legal review" guardrail rather than overriding it under pressure to
monetize real repos: WP-0008-T05 is a dedicated, human-gated go-live
decision, and no other task in any of the three workplans is permitted to
authorize a real Phase, real Commercial Entitlement sale, or real
Development Credit tracking.
Updates SCOPE.md (new Stage 0/Stage 1 maturity table, revised out-of-scope
table distinguishing "infrastructure in scope" from "going live still
gated"), PRD roadmap (Phase 4b/5/7 now active, pointing at the new
workplans), and README's active-work table accordingly.
Co-Authored-By: Claude Sonnet 5 <noreply@anthropic.com>
2026-07-29 20:27:29 +02:00
|
|
|
|
- T01's Licensor-identity question is resolved for whichever product
|
|
|
|
|
|
line goes first;
|
|
|
|
|
|
- `workplans/TREV-WP-0006-trust-service-implementation.md` has a working
|
|
|
|
|
|
hosted Trust Service, or an explicit interim manual/git-based ledger
|
|
|
|
|
|
process is accepted for the pilot instead.
|
|
|
|
|
|
|
|
|
|
|
|
Once accepted, this task's Result should name which specific repo and
|
|
|
|
|
|
Phase go live first — "governance and rollout infrastructure exists" is
|
|
|
|
|
|
not the same event as "a real Phase is declared," and this workplan should
|
|
|
|
|
|
not blur that line even after everything above is ready.
|