# Coulomb, HelixForge and Railiance: factory readiness assessment
|
|||
|
|
|
|||
|
|
Date: 2026-09-08. Assessor: Codex acting as the-custodian.
|
|||
|
|
Scope: the registered Coulomb estate, with particular attention to the HelixForge
|
|||
|
|
delivery path on Railiance. This is an assessment and a proposed programme;
|
|||
|
|
it does not authorize deployment, credentials, reprioritization of other owners,
|
|||
|
|
or unattended execution.
|
|||
|
|
|
|||
|
|
**Assessment:** the estate has enough substantial components to justify an
|
|||
|
|
integration pilot. It does not yet have reviewed evidence that its current
|
|||
|
|
governed execution path repeatedly delivers useful software on Railiance.
|
|||
|
|
The principal constraint is completing and operating the interfaces between
|
|||
|
|
existing components. Starting another general framework would increase the
|
|||
|
|
coordination burden before resolving that constraint.
|
|||
|
|
|
|||
|
|
The recommended outcome is an **internal, single-tenant software factory**:
|
|||
|
|
human intent becomes a bounded capability contract; an authorized agent produces
|
|||
|
|
a reviewable change; independent validation gates an immutable artifact and an
|
|||
|
|
authorized Railiance release; outcome and cost evidence inform the next change.
|
|||
|
|
Autonomous production promotion and external multi-tenant service are later
|
|||
|
|
maturity levels. HelixForge's existing discovery, architecture, and reuse goals
|
|||
|
|
remain part of acceptance: a bot making commits alone does not meet them.
|
|||
|
|
|
|||
|
|
## What was examined, and what the numbers mean
|
|||
|
|
|
|||
|
|
The live State Hub returned 135 repositories, 1,314 workplans and 7,102 tasks.
|
|||
|
|
The separate task-count endpoint also totaled 7,102. Requests used canonical
|
|||
|
|
`/workplans/` and `/tasks/` routes; the task list's default has no pagination
|
|||
|
|
limit in the inspected OpenAPI contract. The inbox for `the-custodian` was empty.
|
|||
|
|
The initial portfolio capture preceded creation of this assessment.
|
|||
|
|
|
|||
|
|
All **94 non-retired open Hub workplans** were resolved to local source files
|
|||
|
|
by UUID or canonical identifier, and their workplan statuses agreed. This
|
|||
|
|
validates the workplan count against available checkouts, not each completion
|
|||
|
|
claim or deployment. Detailed integration review covered the current owner
|
|||
|
|
plans, source contracts, and recorded production evidence, particularly the
|
|||
|
|
September 4–8 work. No live cluster acceptance run, credential access, or
|
|||
|
|
independent security audit was performed in this assessment.
|
|||
|
|
|
|||
|
|
The eighteen principal checkouts' revisions and working-copy states are captured
|
|||
|
|
in [checkout provenance](2026-09-08-helixforge-factory/checkout-provenance.json).
|
|||
|
|
Their cached tracking branches showed no ahead/behind difference; no fetch was
|
|||
|
|
performed. State Hub had existing local changes. Under
|
|||
|
|
[ADR-012](../../canon/architecture/adr-012-projection-source-and-preliminary-overlay.md),
|
|||
|
|
local evidence cannot substitute for a fresh Forge-derived production baseline.
|
|||
|
|
|
|||
|
|
Raw Hub counts are **98 open plans: 44 active, 28 blocked, 15 proposed, six ready,
|
|||
|
|
five backlog**. Four open rows have explicitly retired identities. Excluding
|
|||
|
|
those rows gives the following planning baseline; it is not a silent repair of
|
|||
|
|
the Hub or a claim that all remaining effort is necessary.
|
|||
|
|
|
|||
|
|
| Workplan status | Non-retired count |
|
|||
|
|
| --- | ---: |
|
|||
|
|
| Active | 41 |
|
|||
|
|
| Blocked | 27 |
|
|||
|
|
| Proposed | 15 |
|
|||
|
|
| Ready | 6 |
|
|||
|
|
| Backlog | 5 |
|
|||
|
|
| **Open total** | **94** |
|
|||
|
|
|
|||
|
|
The raw 98 span 49 registered repos. The 94 canonical open plans contain
|
|||
|
|
**264 open tasks: 136 todo, 28 progress, 100 wait**. Across *all* Hub workplans
|
|||
|
|
there are 287 open tasks, including seven attached to retired open identities
|
|||
|
|
and sixteen attached to terminal workplans. Those extra 23 must not be treated
|
|||
|
|
automatically as new implementation demand.
|
|||
|
|
|
|||
|
|
One additional local active record, `kings-guard/KG-WP-0005`, was absent from the
|
|||
|
|
captured Hub workplan list. The wider local scan encountered historic terminal
|
|||
|
|
spellings (`done`, `completed`), shared paths, unavailable registered paths and
|
|||
|
|
legacy YAML dialects. Accordingly, this report uses the verified Hub cohort,
|
|||
|
|
not a purported complete source-only fleet census. Age of a declared update or
|
|||
|
|
sync is not elapsed blocker time; blocker transition history was not measured.
|
|||
|
|
|
|||
|
|
Evidence and reproducible definitions: [baseline](2026-09-08-helixforge-factory/baseline.json),
|
|||
|
|
[98-row inventory](2026-09-08-helixforge-factory/open-workplans.csv),
|
|||
|
|
[source records](2026-09-08-helixforge-factory/source-records.json), and
|
|||
|
|
[methodology](2026-09-08-helixforge-factory/README.md).
|
|||
|
|
|
|||
|
|
## Where the load sits
|
|||
|
|
|
|||
|
|
These are disjoint analytical cohorts, not a proposed repository reclassification.
|
|||
|
|
All statuses in this table exclude retired identities.
|
|||
|
|
|
|||
|
|
| Cohort | Open plans | Active | Blocked | Open tasks |
|
|||
|
|
| --- | ---: | ---: | ---: | ---: |
|
|||
|
|
| Identity, policy, custody and audit | 35 | 14 | 13 | 93 |
|
|||
|
|
| Railiance runtime, packages and recovery | 23 | 10 | 10 | 43 |
|
|||
|
|
| Agent execution and coordination | 9 | 7 | 2 | 15 |
|
|||
|
|
| Hub consolidation and work projection | 7 | 2 | 1 | 26 |
|
|||
|
|
| Publishing and community | 7 | 4 | 0 | 38 |
|
|||
|
|
| Other product, commercial and research work | 13 | 4 | 1 | 49 |
|
|||
|
|
| **Total** | **94** | **41** | **27** | **264** |
|
|||
|
|
|
|||
|
|
Identity/security and Railiance account for **58/94 open plans and 23/27 blocked
|
|||
|
|
plans**. The direct agent-execution cohort has only fifteen open tasks spread
|
|||
|
|
across nine plans. This concentration suggests that dependency closure and live
|
|||
|
|
integration offer more immediate value than expanding the runtime feature list.
|
|||
|
|
It does not establish engineering effort: task counts have no common size.
|
|||
|
|
|
|||
|
|
There is additional intake load: **54 open and eight routed intakes**, including
|
|||
|
|
31 open intakes marked `origin: residual`. Routed intakes may already have
|
|||
|
|
child workplans; adding them to the 94 would double-count some demand.
|
|||
|
|
The [cohort membership](2026-09-08-helixforge-factory/cohorts.json) and full
|
|||
|
|
inventory make the boundaries and individual blocked plans inspectable.
|
|||
|
|
|
|||
|
|
## Existing capabilities worth building on
|
|||
|
|
|
|||
|
|
| Capability | Evidence and practical limit |
|
|||
|
|
| --- | --- |
|
|||
|
|
| HelixForge intent and reusable operating prompts | [INTENT](../../../helix-forge/INTENT.md) defines discovery, capability contracts, architecture validation, realization and evolution. [HF-WP-0005](../../../helix-forge/workplans/HF-WP-0005-reusable-prompt-collection.md) delivered seven prompt packages and two fragments. All five HelixForge workplans are terminal; none owns factory acceptance. Its [SCOPE](../../../helix-forge/SCOPE.md) still describes a concept repository and references the retired Inter-Hub/nested State Hub structure. |
|
|||
|
|
| Forgejo CI and artifact publication | [Runner substrate](../../../railiance-forge/docs/forgejo-actions-runner-substrate.md) records an in-cluster Railiance runner. [Enablement templates](../../../railiance-enablement/docs/forgejo-actions-workflow-templates.md) provide existing build/publish patterns. REINAH-WP-0003 records a recent real CI contract gate. There is no need to propose installing a forge or generic CI from scratch. |
|
|||
|
|
| Scheduled work and repository mutation | [rein-aharness SCOPE](../../../rein-aharness/SCOPE.md) records the real railiance01 user-service claim loop, transaction acceptance and durable terminal-close outbox. Its Kubernetes Deployment runs `sleep infinity`; pod existence is not worker execution evidence. Historical Claude and deterministic clone/commit proofs do not certify the present profile. |
|
|||
|
|
| Governed profile and sandbox boundary | [SAND-WP-0015](../../../sand-boxer/workplans/SAND-WP-0015-bwrap-runtime-and-private-state.md) records real bwrap startup, private state, constrained proxy transport, synthetic credential delivery and a pinned Claude candidate. The candidate remains a local `/tmp` artifact; startup is not a provider request or production installation. |
|
|||
|
|
| Shared runtime substrate | [RMASTER-WP-0020](../../../railiance-master/workplans/RMASTER-WP-0020-openbao-migration-to-reef-railiance.md) records completed OpenBao restore, consumer migration, cutover and reversible source retirement. [RPF-WP-0038](../../../railiance-platform/workplans/RPF-WP-0038-forgejo-scaleway-primary-coverage.md) records successful isolated Forgejo recovery. Remaining cleanup, scheduled custody and retention work must be distinguished from initial deployment. |
|
|||
|
|
|
|||
|
|
## Inefficiencies to tackle
|
|||
|
|
|
|||
|
|
### 1. The queue describes work better than it dispatches it
|
|||
|
|
|
|||
|
|
Only **four of 94** dependency queries returned structured edges, four edges in
|
|||
|
|
total. The owner plans contain many more dependencies in prose. Every one of
|
|||
|
|
the **105 waiting tasks** in the fleet has an empty structured `blocking_reason`.
|
|||
|
|
All 287 open tasks have no API `assignee`; workplans often name owners in
|
|||
|
|
frontmatter or prose, so this is a dispatchability gap, not proof of ownerless work.
|
|||
|
|
**23 of 41 active plans have no task in progress**. That is a review signal,
|
|||
|
|
not an automatic instruction to close or demote them.
|
|||
|
|
|
|||
|
|
All 94 canonical plans show `manual` execution and launch metadata. This does
|
|||
|
|
**not** mean no automation exists: [STATE-WP-0079](../../../state-hub/workplans/STATE-WP-0079-retirement-strangler.md)
|
|||
|
|
records that the old workplan launch route was retired because Activity Core
|
|||
|
|
never consumed it. Factory work must enter the supported ActivityDefinition /
|
|||
|
|
`ops_run` route with explicit admission. Toggling a Hub workplan flag cannot
|
|||
|
|
create an execution path.
|
|||
|
|
|
|||
|
|
**Remedy:** initially normalize only the selected factory chain. Each blocking
|
|||
|
|
task needs the supplying owner task, precise return evidence, next action,
|
|||
|
|
review/expiry condition and whether human action is actually required. Preserve
|
|||
|
|
that information in owning source files and project dependency references; use
|
|||
|
|
existing projection support where available. Do not add another scheduler or
|
|||
|
|
permanent queue to the retiring State Hub. Generate views from those records.
|
|||
|
|
|
|||
|
|
### 2. Human attention is consumed by stale and incomplete signals
|
|||
|
|
|
|||
|
|
Of nineteen `needs_human` flags, **seventeen are terminal tasks** (sixteen done,
|
|||
|
|
one cancelled). Only two are on open tasks. Meanwhile the current owner records
|
|||
|
|
describe real attended custody and verification needs that do not appear in
|
|||
|
|
that queue. Thirteen canonical open plans have no `backing_synced_at`; another
|
|||
|
|
27 have a recorded sync older than seven days. Source status agreement makes
|
|||
|
|
this a provenance/freshness problem, not proof that forty plans are wrong.
|
|||
|
|
|
|||
|
|
Four retired open rows inflate the portfolio: three historical Railiance
|
|||
|
|
Platform identities and the Custodian's retired August 25 ad-hoc identity.
|
|||
|
|
Three non-retired terminal plans also contain open tasks (`SAND-WP-0003`,
|
|||
|
|
`SAND-WP-0005`, `REUSE-WP-0019`); verify source and residual disposition before
|
|||
|
|
changing anything.
|
|||
|
|
|
|||
|
|
The session-close `statehub fix-consistency` check independently returned
|
|||
|
|
**13 assessment failures and 63 warnings** in existing Custodian records:
|
|||
|
|
ten archived CUST-WP-0054 task UUID references, two archived workplan UUID
|
|||
|
|
references, and the retired open ad-hoc identity account for the failures.
|
|||
|
|
It reported zero automation errors and synchronized 75/77 bindings, but it did
|
|||
|
|
**not** pass. The [check receipt](2026-09-08-helixforge-factory/consistency-check.json)
|
|||
|
|
is additional evidence that a healthy API and matching open-plan statuses are
|
|||
|
|
insufficient to establish full historical projection consistency. Existing live
|
|||
|
|
intake [CUST-IN-0017](../../intakes.md) already owns these exact failures and the
|
|||
|
|
prefix conflict; return this observation there during adoption rather than
|
|||
|
|
creating another cleanup workplan.
|
|||
|
|
|
|||
|
|
**Remedy:** review terminal flags and retired identities once through the owning
|
|||
|
|
reconciliation path; preserve history. Present a small, prepared human queue of
|
|||
|
|
actual decisions and attended actions. Batch compatible owner ceremonies when
|
|||
|
|
their prerequisites are ready, with separate grants and receipts. Measure
|
|||
|
|
operator minutes and repeated handoffs, not just the number of closed plans.
|
|||
|
|
|
|||
|
|
### 3. Integration contracts are proved too late
|
|||
|
|
|
|||
|
|
[SECRETS-WP-0009](../../../secrets-engine/workplans/SECRETS-WP-0009-glas-claude-native-delivery.md)
|
|||
|
|
records three concrete discoveries from real owner integration: a missing
|
|||
|
|
tenant, disagreement over normalized request digests, and fixtures that rebuilt
|
|||
|
|
inputs from the expected enriched output. The September 7 correction says the
|
|||
|
|
digest normalization rule was already published; that issue is resolved and
|
|||
|
|
must not be charged again as an outstanding flex-auth dependency.
|
|||
|
|
|
|||
|
|
[AUDIT-WP-0009-T09](../../../audit-core/workplans/AUDIT-WP-0009-evidence-role-conformance.md)
|
|||
|
|
was reprioritized after an inverted dependency was recognized: approval-engine
|
|||
|
|
could not start without its audit sender, although the task had been described
|
|||
|
|
as nonblocking because approval-engine was not yet emitting. The correction is
|
|||
|
|
already recorded. Retelling it as a current unresolved priority dispute would
|
|||
|
|
create more coordination work.
|
|||
|
|
|
|||
|
|
**Remedy:** pin a small cross-owner compatibility set and test real request,
|
|||
|
|
response, credential, admission and completion artifacts early. Require both a
|
|||
|
|
successful path and meaningful denial/retry cases. Consume the existing Glas
|
|||
|
|
handoff packet; do not open a second round of generic owner interviews.
|
|||
|
|
|
|||
|
|
### 4. Locally finished components obscure the missing operating result
|
|||
|
|
|
|||
|
|
[GLAS-WP-0012](../../../glas-harness/workplans/GLAS-WP-0012-first-local-profile-production-proof.md)
|
|||
|
|
is still blocked on first real-profile acceptance; [GLAS-WP-0015](../../../glas-harness/workplans/GLAS-WP-0015-production-dependency-coordination.md)
|
|||
|
|
already coordinates its seven owner interfaces. [APPROVAL-WP-0002](../../../approval-engine/workplans/APPROVAL-WP-0002-production-readiness-and-consumer-adoption.md)
|
|||
|
|
has a published immutable image, but its September 7 review records no deployed
|
|||
|
|
service and outstanding identity/audit inputs.
|
|||
|
|
|
|||
|
|
**Remedy:** use one acceptance ledger linking existing child work and three
|
|||
|
|
distinct evidence levels: source implemented, deployed and exercised, useful
|
|||
|
|
outcome accepted. Close the project only at the third level with repeated
|
|||
|
|
operating evidence. A model-created `SMOKE.md` is a boundary proof; follow it
|
|||
|
|
with a user-valued capability change, release and reuse evidence.
|
|||
|
|
|
|||
|
|
### 5. Concurrent migrations and presentation work compete with the factory path
|
|||
|
|
|
|||
|
|
Hub replacement, security-layer amendments, repository renames, HA, retained
|
|||
|
|
CoulombCore cleanup and publication have legitimate owners and goals. They are
|
|||
|
|
not all prerequisites for one internal factory. The community/publication
|
|||
|
|
cohort alone has 38 open tasks; its commercial importance should be evaluated
|
|||
|
|
explicitly alongside the fifteen direct execution tasks, rather than inferred
|
|||
|
|
from a shared HelixForge name.
|
|||
|
|
|
|||
|
|
**Remedy:** adopt a factory work-in-progress limit: one integrated delivery
|
|||
|
|
item plus at most two prerequisite closures at a time, with an explicit incident
|
|||
|
|
exception. Keep essential operations and security response running. Defer
|
|||
|
|
optional factory expansion, broad renames, full HA, additional model/runtime
|
|||
|
|
families and community automation until the pilot demonstrates delivery. Retain
|
|||
|
|
the current healthy State Hub service while owner migrations meet their own
|
|||
|
|
gates. Avoid another all-estate rename or documentation cleanup programme.
|
|||
|
|
|
|||
|
|
## The actual critical path
|
|||
|
|
|
|||
|
|
This graph is the proposed acceptance sequence, reconstructed from the owner
|
|||
|
|
records. It is not a claim that all these edges are already represented in the
|
|||
|
|
Hub. The local Glas proof must be followed by deployment-specific Railiance
|
|||
|
|
proof; its localhost profile cannot be promoted by changing a label.
|
|||
|
|
|
|||
|
|
```mermaid
|
|||
|
|
flowchart TD
|
|||
|
|
C[Admit service-client custody] --> K[Prove KeyCape approval clients]
|
|||
|
|
A[Admit audit sender and delivery] --> P[Deploy and verify approval-engine]
|
|||
|
|
K --> P
|
|||
|
|
P --> S[Activate native credential lane]
|
|||
|
|
S --> G[Accept real Glas profile]
|
|||
|
|
R[Install pinned runtime and owner policy] --> G
|
|||
|
|
G --> H[Prove current worker on Railiance]
|
|||
|
|
Q[Deploy queue and repository contracts] --> H
|
|||
|
|
H --> D[Useful capability change and independent CI]
|
|||
|
|
D --> B[Immutable artifact and governed Railiance release]
|
|||
|
|
B --> O[Repeat deliveries, recovery and cost observation]
|
|||
|
|
```
|
|||
|
|
|
|||
|
|
| Priority / gate | Existing ownership | Required return and boundary |
|
|||
|
|
| --- | --- | --- |
|
|||
|
|
| Immediate operational risk | `NK-WP-0033`, `NK-WP-0034`, `RPF-WP-0027` | Finish the repaired identity verification receipt and explicit predecessor disposition. Assess overlap before extending a privileged factory lane. The recorded defect is concrete; do not claim the full credential exposure incident closed. |
|
|||
|
|
| Factory identity and audit admission | `KEY-WP-0013-T02`, `AUDIT-WP-0009-T09`, `APPROVAL-WP-0002-T01/T03`; custody owner `railiance-platform` | Exact service clients and consumer-side delivery, agreed audit tenant/redaction policy, admitted sender credential, rollout and restart/restore proof. Glas's platform handoff still lacks a recorded custody return. Link the exact custody record before activation; do not invent a grant from a generic routing match. |
|
|||
|
|
| Native execution credentials | `SECRETS-WP-0009-T03`, linked `SECRETS-WP-0007/0008` | September 7 evidence narrows the remaining external dependency to the approval claim endpoint. Verify claim/consume and actual protected delivery once the service exists. Keep broader engine conformance separate unless its acceptance actually gates this action. |
|
|||
|
|
| Profile acceptance | `SAND-WP-0015-T04`, `GLAS-WP-0012-T02–T06`; coordinator `GLAS-WP-0015-T03` | Protected installation, exact actor/project/profile binding, real provider execution, artifact, denial and teardown receipts. Pinned binary startup and owner transport are already evidenced at candidate level. |
|
|||
|
|
| Railiance worker closure | `REINAH-WP-0003-T05/T06`, `ACTIVITY-WP-0032-T05`, `ACTIVITY-WP-0035-T08`, `ACTIVITY-WP-0036-T04` | Current deployed versions, natural claim/heartbeat/close, controlled late-close rejection, repository acceptance and replay/cleanup. Source heartbeat timing was corrected; return the production trace. |
|
|||
|
|
| Repeated software delivery | HelixForge acceptance owner; source repo; `railiance-enablement`, `railiance-forge`, concrete `rapp-*` / `reef-*` owners | Adopt a bounded implementation record for the chosen pilot after scope selection. Join intent → granted change → CI → immutable artifact → authorized release → service smoke and reuse record. Existing plans do not yet own this whole result. |
|
|||
|
|
|
|||
|
|
Admission does not require completing the entire audit roadmap: AUDIT-WP-0009
|
|||
|
|
explicitly separates sender admission from attestation freshness, heartbeat and
|
|||
|
|
reconciliation claims. Full operating acceptance must address those later
|
|||
|
|
obligations or accurately bound its claims. Likewise OpenBao source deletion,
|
|||
|
|
public UI retraction and factory credential delivery are distinct gates.
|
|||
|
|
|
|||
|
|
## Proposed workplan and first operating target
|
|||
|
|
|
|||
|
|
The complete draft is [HFACT-WP-0001](../proposals/prj-helixforge-factory/workplans/HFACT-WP-0001-establish-internal-factory.md),
|
|||
|
|
with [goal and measurable gates](../proposals/prj-helixforge-factory/GOAL.md).
|
|||
|
|
It is prepared as a dedicated project-repository packet, following
|
|||
|
|
[ADR-005](../../canon/architecture/adr-005-cross-repo-workplans-project-repos.md).
|
|||
|
|
The packet is retained here for review; it has not been instantiated or
|
|||
|
|
registered as another live programme. Existing owner statuses remain intact.
|
|||
|
|
Project adoption is its first task. The permanent product home remains
|
|||
|
|
`helix-forge`; the temporary project coordinates only the missing factory outcome.
|
|||
|
|
|
|||
|
|
Suggested sequencing, with estimates rather than commitments:
|
|||
|
|
|
|||
|
|
| Stage | Completion condition | Rough effort |
|
|||
|
|
| --- | --- | --- |
|
|||
|
|
| Select and normalize | One internal tenant, one pilot service/capability, acceptance owner, execution/spend envelope and exact prerequisite records | 2–3 engineering days |
|
|||
|
|
| Close owner prerequisites | Identity/audit/approval/native delivery and installed runtime proven through current contracts | 4–8 engineering days, plus owner/attended waiting time |
|
|||
|
|
| Prove delivery on Railiance | Current profile and worker, useful code change, independent CI, artifact, authorized release and rollback | 5–8 engineering days |
|
|||
|
|
| Establish operation | Recovery and observability proof, repeatable intake, measurements and acceptance review | 3–5 engineering days plus a 14-calendar-day observation window |
|
|||
|
|
|
|||
|
|
This is roughly **14–24 engineering days plus observation and external waiting**.
|
|||
|
|
A 4–6-week planning window is plausible with two coordinated implementation
|
|||
|
|
tracks and available owners; there is no measured delivery rate or capacity
|
|||
|
|
commitment that makes it a forecast. Do not translate 264 task rows into dates.
|
|||
|
|
|
|||
|
|
Proposed exit: at least five genuinely useful accepted changes across two
|
|||
|
|
repositories during fourteen days, at least one software service release on
|
|||
|
|
Railiance, and a capability reused or consumed by the second repository.
|
|||
|
|
Record every admitted attempt; target ≥80% accepted without operator repair,
|
|||
|
|
≤30 minutes median human handling per accepted change, and ≤30 minutes/day
|
|||
|
|
routine factory operation. Measure security/recovery ceremonies separately and
|
|||
|
|
also include them in total founder load. These are proposed targets, not current
|
|||
|
|
performance. Use `UPC-WP-0003` for the broader company-load objective; a short
|
|||
|
|
factory pilot cannot prove its ≥30-day commercial/company gates.
|
|||
|
|
|
|||
|
|
The first next action is therefore a **prepared custody and audit admission
|
|||
|
|
closure through GLAS-WP-0015**, while the factory owner selects the first useful
|
|||
|
|
capability and its acceptance test. Neither action requires reopening resolved
|
|||
|
|
tenant/digest questions or completing all 94 open plans.
|
|||
|
|
|
|||
|
|
|
|||
|
|
Execution subsequently authorized on 2026-09-08: see the
|
|||
|
|
[implementation return](2026-09-08-helixforge-factory-followthrough.md) and
|
|||
|
|
[current project pointer](../proposals/prj-helixforge-factory/README.md). The
|
|||
|
|
baseline above remains the dated assessment, not a refreshed fleet total.
|