# Weekly Founder Review — 2026-07-21 (prep note)
> Prepared per `OperatingRhythm.md` § Weekly review (~15 min, agent-prepared,
> founder-consumed). Review window: 2026-07-18 → 2026-07-21 (continuation of
> the cycle opened by the 2026-07-18 review).
## Read these (in order)
1. Newest daily brief: `briefs/2026-07-21-daily-brief.md`
2. `SuccessMilestones.md`
## The one question: did anything move a milestone?
**No milestone status changed this window.** `SuccessMilestones.md` is still
unchanged since its v0.1 creation (commit d6d5cf1, 2026-07-16): S1 "in
progress", S2 "started", S3S12 open. No `DecisionQueue.md` entry recorded a
status change.
**Milestone-relevant activity did happen:**
- S2 (active operating system): **BINKY-WP-0005 finished** — first Qonto MCP
read-only pull executed end-to-end (`finance/qonto-first-pull-2026-07-21.json`);
`CostRunRate.md` raised to v2 with real desk-rent and Qonto-fee figures.
- S2 (workstation independence): DEC-2026-003 (executor cutover, retire cron
bridge) remains prepared and unactioned — now 3 days old, all three gates
cleared since 2026-07-18.
## RISK-005 watch
RISK-005 ("agentic stack becomes busywork generator instead of progress
engine") escalates after **two consecutive weeks** of activity without
milestone movement. The 2026-07-18 review flagged week 1 of 2 as high
activity, no milestone status change. This window (through 2026-07-21) is
**still inside week 2** (closes ~2026-07-25) — not yet escalated, but on
track to trigger RISK-005 if the week ending 2026-07-25 also closes without
a milestone status change (or a recorded founder decision that one moved).
Flagging now so it isn't a surprise at the next review.
## Pending founder action (from the 2026-07-21 brief)
- **DEC-2026-003 — Go for executor cutover** (~5 min): all gates cleared,
now the oldest open item in the queue; approval retires the workstation
cron bridge and completes BINKY-WP-0004.
- **OH-2026-003 — Qonto plan cost vs. usage**: numbers are now on the table
(plan fee 70,80 €/mo, desk HUB31 297,50 €/mo, main balance 2 185,94 €);
founder-only call on whether the plan tier is justified. No deadline
pressure — can wait for the next office-hour day.