# Core Hub railiance01 production cutover — 2026-08-21
|
||||
|
||||
Status: in progress; waiting for the operator-owned IONOS DNS edit.
|
||||
|
||||
## Approved boundary
|
||||
|
||||
The operator explicitly approved `CORE-WP-0011-T04`. This gate covers the
|
||||
bounded source write freeze, final transfer, public route change, verification
|
||||
and rollback readiness. CoulombCore resources remain intact through the later
|
||||
stabilization gate.
|
||||
|
||||
## Freeze and final transfer
|
||||
|
||||
- Public DNS still resolves `hub.coulomb.social` to CoulombCore
|
||||
`92.205.130.254`; its observed TTL is 3600 seconds.
|
||||
- CoulombCore database `core_hub` now has
|
||||
`default_transaction_read_only=on`. The source Deployment was restarted,
|
||||
its application role reports `transaction_read_only=on`, and public health
|
||||
and readiness remain HTTP 200.
|
||||
- Frozen full-archive SHA-256:
|
||||
`4015ad622303ba206a46627ba0d03513e1054b95b87247d61cce6cb6b94189e6`.
|
||||
- The data-only transfer contained eight `COPY public.*` streams. Only the
|
||||
statement schema qualifiers were mapped to `core_hub`; the source has no
|
||||
sequence statements.
|
||||
- The target rehearsal state was backed up before its rows were cleared. Its
|
||||
archive SHA-256 is
|
||||
`92200f21d9f9ea01023ec74dd2e64641ec14544ee5a3a024f911c81e2ed67157`.
|
||||
- Restored target counts match the frozen source: `1, 3, 10, 2, 2, 3, 2, 16`
|
||||
across `alembic_version`, `api_consumers`, `api_keys`,
|
||||
`hub_capability_manifests`, `hubs`, `interaction_events`, `migration_runs`
|
||||
and `widgets`.
|
||||
- Order-independent content digests match for all eight tables. Alembic is at
|
||||
`20260627_0002`; the post-restore migration Job completed.
|
||||
|
||||
## Target readiness
|
||||
|
||||
- Helm revision 3 runs chart `0.3.1` at immutable image digest
|
||||
`sha256:0db6f7c646c6d4c1fbc844dc266fcf883584637e1c1f47802efe1c6a98558d3c`.
|
||||
- The railiance01 Deployment is Ready. The hardened package verifier passes.
|
||||
- Direct target resolution returns health/readiness 200, protected hubs 401
|
||||
without authentication, and 200 with the governed token.
|
||||
- The Ingress is present at `92.205.62.239`. Certificate issuance is pending
|
||||
because the IONOS A record still resolves the HTTP-01 challenge to the
|
||||
source host.
|
||||
|
||||
## Current rollback
|
||||
|
||||
Before the DNS edit, rollback is:
|
||||
|
||||
1. Roll railiance01 Helm release `core-hub` back from revision 3 to revision 2
|
||||
to remove the target Ingress.
|
||||
2. On CoulombCore, reset database `core_hub`'s
|
||||
`default_transaction_read_only` setting and restart Deployment
|
||||
`core-hub-api` so the application reconnects writable.
|
||||
3. Verify public health, readiness and an authenticated protected operation.
|
||||
|
||||
After DNS changes, restore `hub.coulomb.social` to `92.205.130.254` before
|
||||
reenabling source writes. Never allow both databases to accept production
|
||||
writes.
|
||||