Core Hub railiance01 production cutover — 2026-08-21

Status: in progress; waiting for the operator-owned IONOS DNS edit.

Approved boundary

The operator explicitly approved CORE-WP-0011-T04. This gate covers the bounded source write freeze, final transfer, public route change, verification and rollback readiness. CoulombCore resources remain intact through the later stabilization gate.

Freeze and final transfer

  • Public DNS still resolves hub.coulomb.social to CoulombCore 92.205.130.254; its observed TTL is 3600 seconds.
  • CoulombCore database core_hub now has default_transaction_read_only=on. The source Deployment was restarted, its application role reports transaction_read_only=on, and public health and readiness remain HTTP 200.
  • Frozen full-archive SHA-256: 4015ad622303ba206a46627ba0d03513e1054b95b87247d61cce6cb6b94189e6.
  • The data-only transfer contained eight COPY public.* streams. Only the statement schema qualifiers were mapped to core_hub; the source has no sequence statements.
  • The target rehearsal state was backed up before its rows were cleared. Its archive SHA-256 is 92200f21d9f9ea01023ec74dd2e64641ec14544ee5a3a024f911c81e2ed67157.
  • Restored target counts match the frozen source: 1, 3, 10, 2, 2, 3, 2, 16 across alembic_version, api_consumers, api_keys, hub_capability_manifests, hubs, interaction_events, migration_runs and widgets.
  • Order-independent content digests match for all eight tables. Alembic is at 20260627_0002; the post-restore migration Job completed.

Target readiness

  • Helm revision 3 runs chart 0.3.1 at immutable image digest sha256:0db6f7c646c6d4c1fbc844dc266fcf883584637e1c1f47802efe1c6a98558d3c.
  • The railiance01 Deployment is Ready. The hardened package verifier passes.
  • Direct target resolution returns health/readiness 200, protected hubs 401 without authentication, and 200 with the governed token.
  • The Ingress is present at 92.205.62.239. Certificate issuance is pending because the IONOS A record still resolves the HTTP-01 challenge to the source host.

Current rollback

Before the DNS edit, rollback is:

  1. Roll railiance01 Helm release core-hub back from revision 3 to revision 2 to remove the target Ingress.
  2. On CoulombCore, reset database core_hub's default_transaction_read_only setting and restart Deployment core-hub-api so the application reconnects writable.
  3. Verify public health, readiness and an authenticated protected operation.

After DNS changes, restore hub.coulomb.social to 92.205.130.254 before reenabling source writes. Never allow both databases to accept production writes.