# Progress assessment for CSOC-WP-0012–0015
|
||
|
||
Assessment date: 2026-10-31. This is an effort estimate against the full four-workplan
|
||
objective, not a task-count percentage or a new acceptance decision.
|
||
|
||
**Working estimate: roughly 60% complete, with about 40% still ahead. A reasonable
|
||
remaining-work range is 35–50%.** Productive review may expose further work; elapsed
|
||
hours, test counts and the number of prepared release packets do not predict that
|
||
rework. This is not a calendar completion promise.
|
||
|
||
## Basis and uncertainty
|
||
|
||
| Workplan | Planning weight | Estimated work remaining | What drives the remainder |
|
||
| --- | ---: | ---: | --- |
|
||
| WP-0012 recovery/service | 35% | 35–45% | Recurring route and inactive installation, native failure/retry/watchdog proof, schedule observation, retention/capacity, complete service registration/cost/offboarding evidence |
|
||
| WP-0013 sharing/content | 20% | 25–40% | Actual corpus/assets fidelity and revision lifecycle acceptance, four productive sharing/portability journeys and any resulting fixes |
|
||
| WP-0014 migration/off-ramp | 30% | 50–65% | Source exceptions and identity/grant/assets mapping, remaining productive cohort transfers and date verification, retained use-case verdicts, separate cutover/retirement decision |
|
||
| WP-0015 communication | 15% | 25–40% | General sender/reply/inbox/DNS/bounce ownership, native reset-authority return, productive registration/invitation acceptance |
|
||
|
||
Weights are an explicit engineering judgment about relative scope, not measured
|
||
historical effort. Weighted bounds are approximately 36–50%; the public estimate
|
||
is deliberately rounded. Do not count final acceptance gates and their detailed
|
||
execution tasks twice. Substantial implementation is complete, but pending native
|
||
operations and productive acceptance are real work. The range assumes existing
|
||
implementations largely survive review and that the remaining source exceptions
|
||
can be resolved without a new platform feature set. More reconstruction or major
|
||
rejected workflows would raise it. Waiting for an owner or observation window can
|
||
extend calendar time without proportionate engineering effort.
|
||
|
||
## Verified progress that the old task counts concealed
|
||
|
||
- Independent encrypted paired recovery, provider-only protected-kit recovery and
|
||
immutable readback have been exercised. Latest corrected-date recovery compares
|
||
13 tables, 114 rows and 86 files, with owner/outsider view checks. See
|
||
`provider-kit-recovery-post-date-2026-10-31.json` and the identity release return.
|
||
- Storage enforcement was deployed and verified at revision 18. The later identity/
|
||
export image release is verified at revision 19 with unchanged business data,
|
||
content and migration history. See `storage-release-review-2026-10-31.md` and
|
||
`identity-export-release-return-2026-10-31.md`.
|
||
- The accepted-cohort date correction is complete, with all 36 imported source
|
||
dates verified and three local pages preserved. See
|
||
`accepted-cohort-date-manifest-proof-2026-10-31.json`.
|
||
- State Hub backup notification readback and the SMTP proof are verified; the user
|
||
confirmed actual Gmail inbox receipt. Recurring delivery source and isolated
|
||
native checks are complete. This does not establish automatic monitoring.
|
||
- All 71 known spaces are retained in inventory, with 67 draft trees and explicit
|
||
unresolved exceptions. Native identity/browser and owner-source communication
|
||
rehearsals pass. Neither preparation nor automated success supplies a productive
|
||
transfer verdict.
|
||
|
||
At the first tracking-audit checkpoint, `make check` reported 475 passed, zero failures/errors/skips,
|
||
including required browser journeys. Fifteen cases cover the source installer
|
||
library. No source code changed during this tracking audit; its source hashes and
|
||
result envelope are in `backup-source-installer-validation-2026-10-31.json`.
|
||
|
||
## Tracking correction and scope conservation
|
||
|
||
Before this audit, 4 of 14 very broad tasks were marked done. Hundreds of lines of
|
||
implementation and deployment receipts accumulated inside the others. State Hub
|
||
received description updates, but its unchanged completion counts hid meaningful
|
||
progress. That was a planning/tracking weakness, not evidence that no work happened.
|
||
|
||
The audit retains every original task ID and evidence trail, adds 16 concrete
|
||
execution/milestone tasks, and splits three broad tasks at verified boundaries:
|
||
|
||
| Original task | Now complete | Remaining original scope remains live in |
|
||
| --- | --- | --- |
|
||
| WP-0012-T01 | Independent custody and protected retrieval | WP-0012-T04 retention, capacity and historical-copy disposition; ongoing service remains T03/T07–T12 |
|
||
| WP-0014-T04 | Accepted live cohort date correction and postflight | WP-0014-T06 remaining trees/dates/productive verification; T07 transfer |
|
||
| WP-0015-T04 | Browser implementation/native rehearsal and verified app release | WP-0015-T05 productive flow verdicts; T06 native reset-authority return |
|
||
|
||
No workplan is finished. New source/rehearsal milestone tasks say explicitly what
|
||
is and is not proved. WP-0012-T03 remains a final service acceptance gate, not a
|
||
second estimate for its detailed implementation tasks. WP-0013-T02 similarly
|
||
consumes T04 preparation and T05 lifecycle acceptance. New task totals are **11
|
||
of 30 done**, useful as a checklist but still unsuitable as effort arithmetic.
|
||
|
||
Central REST readback at 10:18:38Z verifies all 30 task titles, statuses and
|
||
human-action flags against the source files, and all four workplans remain active.
|
||
Receipt: `goal-progress-statehub-2026-10-31.json`. `statehub fix-consistency`
|
||
synchronized the task records and regenerated the work-record index; the three
|
||
renamed titles were explicitly reconciled from the files because that command
|
||
does not synchronize existing task titles.
|
||
|
||
Next task state changes must occur at the named milestone: execution receipt,
|
||
independent postflight, native recurring run, or explicit productive verdict.
|
||
Any failed review becomes a concrete live task. Progress updates should name
|
||
which task advanced and its next closure condition, rather than only append a
|
||
long session narrative.
|
||
|
||
## Immediate sequence
|
||
|
||
1. WP-0012-T07: receive and verify the existing attended telemetry route execution.
|
||
Its receipt was absent at the latest native observation (10:04:37Z). The reviewed
|
||
packet and digest4d848106 are unchanged; this audit performs no privileged action.
|
||
2. WP-0012-T08/T04: finish the supervised inactive installer and resolve operating
|
||
retention/capacity requirements. Source primitives are complete; installation
|
||
and timer activation have not occurred.
|
||
3. WP-0012-T09/T10: prove native capture and failure reception, then activate and
|
||
observe the already approved schedule after its prerequisites are met.
|
||
4. Resume WP-0013 fidelity/journey review and WP-0014 source-exception/cohort work;
|
||
prepare WP-0015 productive flow and general sender ownership returns. These
|
||
lanes are not completed by backup work and must remain visible.
|
||
|
||
There is no need to rerun completed storage, date, image or one-off email commands,
|
||
or to approve the already settled alert destinations and schedule again.
|
||
|
||
## Topic visibility correction — October 31 follow-through
|
||
|
||
A later orientation check found that all four workplans had the correct Coulomb
|
||
repository ID but the **Markitect topic ID**, despite their authoritative
|
||
`topic_slug: coulomb-social`. The topic-filtered query in AGENTS therefore omitted
|
||
these plans. The earlier task/status readback did not test topic associations.
|
||
|
||
Corrected only the four existing workplan topic links to the declared Coulomb
|
||
topic, preserving IDs, repository bindings, statuses, task references and backing
|
||
files. The original AGENTS topic query now returns all four active goal workplans.
|
||
Proof: `goal-topic-reconciliation-2026-10-31.json`. This is an additional tracking
|
||
defect, separate from the oversized tasks corrected above. It does not change the
|
||
effort estimate or imply that unfinished work has completed.
|
||
|
||
The shared State Hub C-06 creation path currently chooses the first topic matching
|
||
a domain instead of the declared topic slug. That code is not changed by this
|
||
projection correction; future newly registered plans need an explicit topic
|
||
readback until the owner fixes that selection.
|
||
|
||
## Producer-custody follow-through
|
||
|
||
Subsequent installer preflight identified eight historical metadata exceptions.
|
||
The exact repair is prepared with passing native preflight, but awaits its attended
|
||
execution. A separate completed source task, WP-0012-T13, now prevents recurrence
|
||
in current release and date-operation producers; its release-owner return is
|
||
RAPPS-WP-0015-T06. Evidence: backup-producer-custody-validation-2026-10-31.json.
|
||
This makes the source checklist **12 of 31 done**. The extra task exposes a discovered
|
||
correction, not a new user-facing capability or a revised effort percentage.
|
||
|
||
WP-0012-T07 remains wait for the reviewed recurring route execution. T08 preparation
|
||
is complete and waits on T04 historical custody/capacity and T07. T04 remains in
|
||
progress for those native returns and historical-copy disposition. The original
|
||
roughly 40% remaining estimate is unchanged: these source fixes do not establish
|
||
recurring operation, productive acceptance or full remaining-cohort transfer.
|
||
|
||
|
||
## Service provenance checkpoint
|
||
|
||
WP-0012-T14 now closes the Forgejo successor and existing founder identity-choice
|
||
bindings formerly inside T11. The records include resolved decisions, completed
|
||
owner migration and fresh read-only native metadata. T11 advances to progress and
|
||
retains actual ops registration, client/app/instance finance attribution/report,
|
||
current SLO and stage-1 smoke. This makes the source checklist13of32done; it is an
|
||
additional independently verified requirement, not a new product scope or an
|
||
updated effort estimate. The rough remaining-work estimate is unchanged.
|
||
|
||
|
||
## Visual preservation checkpoint
|
||
|
||
WP-0014-T08 completes the previously missing private Visual capture and draft-tree
|
||
materialization:242references,108URLs,90distinct images,236article pages and67
|
||
space indexes. Offline decoding and independent body/date/source preservation
|
||
checks pass. This advances the source checklist to14of33done, not an effort
|
||
percentage. Source exceptions, identity/grant mapping, links/attachments and
|
||
productive transfer/verdicts remain open; the rough remaining-effort estimate
|
||
has not been recalculated from these counts.
|
||
|
||
## Access reconciliation checkpoint
|
||
|
||
WP-0014-T01 now has a private, source-hash-bound access inventory covering the
|
||
70 fresh spaces and 245 articles, while retaining the inventory-only 71st space.
|
||
It identifies three distinct source principals and nine unresolved creator
|
||
references, preserving missing access fields as unknown. Existing ReichelAG
|
||
admission does not establish all-space identity or role mappings. The task remains
|
||
progress: this closes an evidence gap inside the task, not productive permission
|
||
reconciliation. The checklist stays 14 of 33 done, and the remaining-effort
|
||
estimate is unchanged. Evidence: `bubble-access-audit-2026-10-31.json`.
|
||
|
||
## Offboarding scope checkpoint
|
||
|
||
WP-0012-T12 moves from todo to progress with a concrete non-destructive scope
|
||
review. Fresh native evidence distinguishes the accepted85file tenant export from
|
||
the second, externally bound space; confirms the Helm-retained content PVC; and
|
||
accounts for five still-running isolated recovery databases and their receipts.
|
||
The review includes sessions, root journals, private copies and protected backup
|
||
holds. No teardown, deletion, revocation or expiry occurred. Canonical client
|
||
scope, agreed retention, procedure proof and private delivery/acceptance remain
|
||
open. The checklist stays14of33done; the effort estimate is unchanged. Evidence:
|
||
`client-offboarding-scope-2026-10-31.json` and its human-readable scope review.
|