prj-state-hub-retirement/WORK-RECORDS.md
tegwick bf2b8f08ce SHR-WP-0002: correct the premise — gen 2 was retired properly
T01 executed and disproved the workplan's own first draft. core-hub's archive
shows CORE-WP-0005 closed the production cutover gates on 2026-07-03 and
CORE-WP-0007 retired the Haskell/IHP infrastructure by 2026-07-08, with a
stabilization window and explicit operator approval to retire the Inter-Hub
rollback deployment. The 0/0 Deployment on railiance01 is that rollback standby
at its designed end state, not a lapse.

The surviving finding is sharper and more urgent: hub.coulomb.social resolves to
92.205.130.254 — CoulombCore — so Core Hub's production runtime, in service since
July, sits on the host being decommissioned, with no core-hub presence on
railiance01 and hub-core still a package rather than a service. The workplan is
retitled and re-centred on that.

DECISIONS.md records the correction and why it generalises: the live documents
described a retirement that had already happened while the completed evidence sat
in an archived workplan, so a reader checking current files reaches the wrong
conclusion. That requirement applies directly to the State Hub retirement this
project is planning.

Co-Authored-By: Claude Opus 5 <noreply@anthropic.com>
2026-08-20 08:07:53 +02:00

1.7 KiB

Work Records — prj-state-hub-retirement

Generated by statehub fix-consistency (CUST-WP-0061-T04, work-record stage 3). Do not edit by hand — edit the source file/block listed for each record and re-run fix-consistency to refresh this index. Archived workplans are omitted; closed decisions/intakes/engagements stay listed so recently-resolved work is still visible. [auto]

Kind ID Status Lane Source
workplan SHR-WP-0001 finished workplans/SHR-WP-0001-foundation.md
workplan SHR-WP-0002 proposed workplans/SHR-WP-0002-predecessor-and-deployment-reality.md
task SHR-WP-0001-T01 done workplans/SHR-WP-0001-foundation.md
task SHR-WP-0001-T02 done workplans/SHR-WP-0001-foundation.md
task SHR-WP-0001-T03 done workplans/SHR-WP-0001-foundation.md
task SHR-WP-0001-T04 done workplans/SHR-WP-0001-foundation.md
task SHR-WP-0001-T05 done workplans/SHR-WP-0001-foundation.md
task SHR-WP-0001-T06 done workplans/SHR-WP-0001-foundation.md
task SHR-WP-0002-T01 todo workplans/SHR-WP-0002-predecessor-and-deployment-reality.md
task SHR-WP-0002-T02 todo workplans/SHR-WP-0002-predecessor-and-deployment-reality.md
task SHR-WP-0002-T03 todo workplans/SHR-WP-0002-predecessor-and-deployment-reality.md
task SHR-WP-0002-T04 todo workplans/SHR-WP-0002-predecessor-and-deployment-reality.md
task SHR-WP-0002-T05 todo workplans/SHR-WP-0002-predecessor-and-deployment-reality.md
task SHR-WP-0002-T06 todo workplans/SHR-WP-0002-predecessor-and-deployment-reality.md