id: UPC-GATE-MAP-0001
|
||
type: gate-map
|
||
repo: prj-unattended-progress-company
|
||
parent_workplan: UPC-WP-0001
|
||
repo_goal_id: "79a2b057-b765-47ad-b5d9-c1bbc49eba43"
|
||
created: "2026-08-11"
|
||
reviewed: "2026-08-11"
|
||
---
|
||
|
||
# Gate-to-evidence map (G1–G9)
|
||
|
||
Maps every `GOAL.md` success gate to owning repos, known child workplans /
|
||
queues, evidence pointers, status, and blockers. **Link by ID only** — task
|
||
lists live in the owning repos.
|
||
|
||
Status vocabulary: `open` | `partial` | `met`.
|
||
|
||
| Gate | Title | Owning repo(s) | Known child workplans / loops | Evidence path or missing | Status | Blockers |
|
||
| --- | --- | --- | --- | --- | --- | --- |
|
||
| **G1** | Administratively clean | `binky-control` | BINKY-WP-0002 (done); OH-2026-001…005; RISK-006/007; Phase 1 checklist | `CompanyReactivationPlan.md` Phase 1; `audits/OK-Audit-v0-binky.md`; `finance/CostRunRate.md` + Qonto pull; OH queue items prepared — **Handelsregister verify, StB mandate, DUO transition still open** | **partial** | Orange: StB, DUO, Handelsregister, Qonto review; Red: bank plan changes, notary if purpose change |
|
||
| **G2** | Company OS active | `binky-control` | BINKY-WP-0001…0003 (done); OperatingRhythm; DecisionQueue; OfficeHourQueue; AutopilotWorkQueue; ControlLoopCatalog | `INTENT.md` v1.0 ratified DEC-2026-001; `AutonomyPolicy.md`; daily briefs through 2026-08-08; queues live | **partial** → near met | Policy “in force” is operationally true; formal checklist still marks some governance boxes open in Reactivation Plan |
|
||
| **G3** | Dogfood loop closed | `binky-control`, Railiance/`activity-core`/`llm-connect` | BINKY-WP-0003…0006 (finished); REIN-A-0003 weekly review | OK-Audit v0 dogfood; rhythm on Railiance without host coding agent; ops_run `ad0b05c4-…` weekly review proof 2026-08-08 | **partial** → strong | Need a named “S3 acceptance” evidence pack in this project; founder milestone status still ⬜ on S3 |
|
||
| **G4** | Founder load within budget | `binky-control` (measure), this project (gate evidence) | *none dedicated* | **missing** — no ≥30-day CEO time envelope log / KPI | **open** | Design + measure load; requires definition of what counts as “routine company ops” vs Red exceptions |
|
||
| **G5** | External offer published | `binky-control` (+ website/domain as needed) | BINKY-WP-0002-T04 (draft done); OfferCatalog flagship | `OfferCatalog.md` — OK Audit **drafted**, publishing Yellow-lane decision package **not closed** | **open** | Yellow decision to publish; domain/website residual (AWQ-003, Reactivation digital presence) |
|
||
| **G6** | First paid revenue | `binky-control`, finance path | BINKY-WP-0005/0007 (Qonto read path finished) | Qonto evidence of costs/credits; Binect-related credit noted — **no booked external product/service sale** | **open** | Depends on G5 + delivery; Red for contracts/payment setup if needed |
|
||
| **G7** | Repeatable path | product/service repos after first delivery | *gap* | **missing** unit economics / productized delivery after first sale | **open** | Premature until G5–G6; residual to durable product repos |
|
||
| **G8** | Decision surface thin | `binky-control` | DecisionQueue hygiene; OH batching; AutonomyPolicy lanes | DecisionQueue: prepared items resolved pattern; OH: 5 prepared items batched; AWQ mostly closed/optional | **partial** | Material admin still blocked on Orange OH batch (not “nobody asked Bernd” — but not thin until G1 OH drain) |
|
||
| **G9** | Residuals owned outside project | all participating repos | work-record residual convention; AWQ residual intakes | Pattern exists (e.g. AWQ residuals with `origin_ref`); **project not complete** so gate open by definition | **open** | Close only at project retirement; enforce residual handoff as each UPC-WP finishes |
|
||
|
||
## Cluster view (for sequencing)
|
||
|
||
| Cluster | Gates | Dominant state | Coordination home |
|
||
| --- | --- | --- | --- |
|
||
| Company vessel | G1, residual G2 | G1 blocks clean vessel | **UPC-WP-0002** (drafted) |
|
||
| Unattended + load | G3, G4 | G3 strong; G4 missing | future UPC-WP-0003 |
|
||
| Revenue path | G5, G6, G7 | Offer drafted only | future UPC-WP-0004 |
|
||
| Governance close | G8, G9 | partial / endgame | continuous + retirement |
|
||
|
||
## Update rule
|
||
|
||
When a child workplan finishes or an OH/DEC item closes, update **Status** and
|
||
**Evidence** here (or via a dated note under `inventory/`). Do not expand
|
||
child task prose into this map.
|