| id | type | title | domain | repo | status | owner | topic_slug | created | updated | state_hub_workstream_id |
|---|---|---|---|---|---|---|---|---|---|---|
| RAILIANCE-WP-0014 | workplan | Core Hub Helm cutover and vergabe-teilnahme image refresh | financials | railiance-apps | active | codex | railiance | 2026-07-10 | 2026-07-11 | 780c8d1d-ea75-479e-9733-10b518dde242 |
Core Hub Helm cutover and vergabe-teilnahme image refresh
Follow-up to RAILIANCE-WP-0012 and custodian inbox 3ced85c7. The S5 Helm
chart, values, Makefile targets, and runbook exist; the live cluster may still
run Core Hub from core-hub/k8s/railiance-production/ manifests.
Separately, the 2026-07-10 delivery-lane snapshot shows vergabe-teilnahme
deployed at f95de14 while the source repo head is 1061f3e (14-commit drift).
Production-touching deploy steps require explicit image tags and operator approval. Do not store secrets in workplans.
Core Hub server dry-run on CoulombCore
id: RAILIANCE-WP-0014-T01
status: done
priority: high
state_hub_task_id: "b9dea9f3-f0c0-41c1-b9c4-ec4c44d43d55"
CoulombCore production cluster confirmed. core-hub-server-dry-run passed after
make core-hub-helm-adopt and configMap name alignment (core-hub-prod-runtime).
Live image gitea.coulomb.social/coulomb/core-hub:a33191a verified.
Adopt Helm-managed Core Hub release
id: RAILIANCE-WP-0014-T02
status: done
priority: high
state_hub_task_id: "0e591104-0123-4e4a-84ff-5deb435e8441"
CORE_HUB_IMAGE_TAG=a33191a make core-hub-deploy installed Helm release
core-hub revision 1 on CoulombCore. Resources carry Helm ownership metadata.
Service-repo k8s/railiance-production/ path is now superseded for operations.
Verify Core Hub post-cutover smoke
id: RAILIANCE-WP-0014-T03
status: done
priority: high
state_hub_task_id: "eca3ce8b-68a8-44d0-90c7-2cdefa482200"
Post-deploy make core-hub-status and make core-hub-smoke passed on
https://hub.coulomb.social after Helm rollout (2026-07-10).
Refresh vergabe-teilnahme production image
id: RAILIANCE-WP-0014-T04
status: progress
priority: medium
state_hub_task_id: "d547f68d-52ec-4ff1-952b-ec70c834e0d3"
2026-07-11: Migrated deploy target to Forgejo OCI (forgejo.coulomb.social).
Added .forgejo/workflows/image.yaml in vergabe-teilnahme; Makefile
check-vergabe-image gates deploy. helm/vergabe-teilnahme-values.yaml targets
Forgejo repository + tag dfbc13a.
2026-07-12: CI root cause fixed — Forgejo Actions run failed because
uv sync resolved issue-core from Forgejo PyPI (404). Fix: uv sync --frozen
in vergabe-teilnahme Dockerfile (dfbc13a); workflow aligned with
railiance-enablement container-build template. Local docker build verified.
issue-core gained publish-forgejo + .forgejo/workflows/publish-python-package.yml
so PyPI can move off Gitea (uv.lock still pins Gitea wheel URLs until publish).
Remaining: push forgejo.coulomb.social/coulomb/vergabe-teilnahme:dfbc13a
(CI on railiance01 or docker login + docker push), then
VERGABE_IMAGE_TAG=dfbc13a make vergabe-deploy. Live cluster still
gitea...:f95de14.
Post-deploy vergabe smoke and runbook evidence
id: RAILIANCE-WP-0014-T05
status: wait
priority: medium
state_hub_task_id: "4eaaa345-4252-46c1-bd8a-49d654ec48f4"
After deploy, run make vergabe-status, migrations if required, and HTTPS smoke
against vergabe-teilnahme.whywhynot.de. Update docs/vergabe-teilnahme.md
with the deployed tag, date, and smoke result (non-secret).
Blocked on: RAILIANCE-WP-0014-T04.