Set up practical implementation workplans (WP-0006/0007/0008)

With WP-0001/0002/0003 finished, PRD Phase 4b (hosted Trust Service) is
unblocked per SCOPE.md's own sequencing rule, and the midterm goal shifts
from framework design to practical application: governing and monetizing
repos across the coulomb Forgejo org's product lines (coulomb-loop,
net-kingdom, helix-forge, the railiance-* family).

- TREV-WP-0006: Trust Service reference implementation (PRD Phase 4b).
  Eight tasks from PRD to conformance-tested hosted service, explicit that
  it builds infrastructure only - no real payments or Phase tracking.
- TREV-WP-0007: Degeneration policy finalization (PRD Phase 5) and the
  full canonical monetization profile catalog (remainder of Phase 3) -
  pilot Phases can't responsibly launch on the placeholder pilot policy
  and one-line profile defaults alone.
- TREV-WP-0008: Governance formalization (PRD Phase 7) and pilot rollout
  preparation. Forces a real design decision the framework never had to
  answer while single-repo-hypothetical: who is "the Licensor" across four
  independent product lines. Produces draft, non-binding Phase Manifests
  as worked examples for one repo per product line, and a CLA draft.

All three explicitly preserve SCOPE.md's existing "no production Phases
until legal review" guardrail rather than overriding it under pressure to
monetize real repos: WP-0008-T05 is a dedicated, human-gated go-live
decision, and no other task in any of the three workplans is permitted to
authorize a real Phase, real Commercial Entitlement sale, or real
Development Credit tracking.

Updates SCOPE.md (new Stage 0/Stage 1 maturity table, revised out-of-scope
table distinguishing "infrastructure in scope" from "going live still
gated"), PRD roadmap (Phase 4b/5/7 now active, pointing at the new
workplans), and README's active-work table accordingly.

Co-Authored-By: Claude Sonnet 5 <noreply@anthropic.com>
This commit is contained in:
tegwick 2026-07-29 20:27:29 +02:00
parent cdfdd7f6b3
commit dd7f7d2181
6 changed files with 442 additions and 27 deletions

View file

@ -0,0 +1,147 @@
---
id: TREV-WP-0008
type: workplan
title: "Governance formalization and pilot rollout (coulomb / net-kingdom / helix-forge / railiance)"
domain: infotech
repo: target-revenue
status: active
owner: claude
topic_slug: infotech
created: "2026-07-29"
updated: "2026-07-29"
---
# Governance formalization and pilot rollout
The midterm goal: govern and monetize the evolution of repos across the
`coulomb` Forgejo org's product lines — `coulomb-loop`, `net-kingdom`,
`helix-forge`, and the `railiance-*` family (`railiance-apps`,
`railiance-bootstrap`, `railiance-cluster`, `railiance-enablement`,
`railiance-fabric`, `railiance-forge`, `railiance-hosts`, `railiance-infra`,
`railiance-master`, `railiance-platform`). This workplan formalizes the
governance the framework has been designed around but never actually
written down, and prepares (but does not itself execute) the first real
Phase declarations.
**Hard gate, stated up front:** `SCOPE.md` §3 lists "governing third-party
product Phases in production" as out of scope "after legal + Stage 0
package ready" — i.e., not yet. This workplan's rollout tasks (T03–T04)
produce **draft, non-binding** Phase Manifests as worked examples, exactly
like `examples/phase-001/` already is. **No real Commercial Entitlement may
be sold, no real Development Credit tracked, and no repo's actual License
header changed to TRSL, until T05 (the go-live gate) is explicitly
accepted** — after TRSL/CUA specialist legal review (`workplans/TREV-WP-0004-global-jurisdiction-research.md` /
`workplans/TREV-WP-0005-enforcement-network-research.md` T10 syntheses
feed this) and T01 (Licensor governance) are both resolved. Moving fast on
T01–T04 must not create pressure to skip T05.
## Governance document: TRSL-Governance.md
```task
id: TREV-WP-0008-T01
status: todo
priority: high
```
Produce `specs/TRSL-Governance.md`, per `spec/TargetRevenueLicenseConcept.md`
§20 (complexity budget, versioning, extension governance, operator
governance). Must resolve one question this rollout makes concretely
unavoidable for the first time: **who is "the Licensor"** across four
different product lines under one Forgejo org — a single shared Licensor
entity for all four (simplest, but conflates genuinely different products'
commercial decisions), or a per-product-line Licensor (each of
`coulomb-loop`, `net-kingdom`, `helix-forge`, `railiance` declaring its own
Phases independently under a shared TRSL/CUA template)? This was never
forced while the framework was single-repo-hypothetical; it is now.
Also define: change process for the License/CUA templates themselves once
multiple product lines depend on them, extension canonicalization review
(coordinate with `workplans/TREV-WP-0007-degeneration-policy-and-canonical-profiles.md`
T04's narrower checklist), and dispute/conflict-of-interest handling per
concept §20.3–§20.4.
## Repo inventory and Phase-candidate survey
```task
id: TREV-WP-0008-T02
status: todo
priority: high
```
For each of `coulomb-loop`, `net-kingdom`, `helix-forge`, and the
`railiance-*` family: survey current repo goals and status (via the state
hub's `get_domain_summary`/`list_domain_repos`/repo-goal tools, or direct
repo inspection where hub data is thin) to identify one plausible first
Milestone Release candidate per product line — a bounded, recently- or
soon-to-be-completed piece of work with a defensible Target Multiple
classification (`specs/TargetRevenueFrameworkCore.md` §1.4), not an
arbitrary pick. Document why each candidate was chosen and what was
passed over.
## Draft pilot Phase Manifests (non-binding worked examples)
```task
id: TREV-WP-0008-T03
status: todo
priority: high
```
Using T02's candidates, draft one Phase Manifest per product line
following `specs/PhaseManifestSpecification.md` and
`schemas/phase_manifest.schema.json` exactly — structurally valid,
conformance-tested the same way `examples/phase-001/` is, but explicitly
marked **draft / not yet declared** (no real Commercial Use restriction
takes effect from these). Choose an applicable Monetization Extension per
Phase from `workplans/TREV-WP-0007-degeneration-policy-and-canonical-profiles.md`
T03's catalog.
## Contributor rights instrument (CLA)
```task
id: TREV-WP-0008-T04
status: todo
priority: medium
```
`CONTRIBUTING.md` currently blocks external contributions into any
governed Milestone Release until a contributor-rights instrument exists
(per `history/260729-TRSL-ContributorRights-Research.md`). If any pilot
candidate from T02 has, or expects, external contributors before its
Conversion Event, this is now practically blocking, not theoretical.
Produce `specs/TRSL-ContributorLicenseAgreement-Draft.md`: a CLA scoped
narrowly to the current Phase's TRSL terms plus its already-declared
Future License, per the T04 research's recommendation. Same preliminary-
candidate treatment as the License/CUA V1C1 documents (status banner,
Appendix A-style candidate notes) — this is a new legal document, not
exempt from that pattern.
## Go-live gate (human decision)
```task
id: TREV-WP-0008-T05
status: todo
priority: high
human_accept_required: true
```
**Do not mark this task done to authorize real Phase declarations.** It
exists to make the go-live decision a single, explicit, recorded moment
rather than something that happens by accretion once enough pilot
infrastructure exists. Before acceptance, confirm:
- `workplans/TREV-WP-0004-global-jurisdiction-research.md` T10 and
`workplans/TREV-WP-0005-enforcement-network-research.md` T10 syntheses
are complete, or their absence is an explicitly accepted risk;
- specialist legal review of `specs/TargetRevenueSourceLicense-V1C1.md`
and `specs/TargetRevenueCommercialUseAgreement-V1C1.md` (condition 1 in
each document's status banner) has occurred, or is explicitly waived for
a defined pilot scope;
- T01's Licensor-identity question is resolved for whichever product
line goes first;
- `workplans/TREV-WP-0006-trust-service-implementation.md` has a working
hosted Trust Service, or an explicit interim manual/git-based ledger
process is accepted for the pilot instead.
Once accepted, this task's Result should name which specific repo and
Phase go live first — "governance and rollout infrastructure exists" is
not the same event as "a real Phase is declared," and this workplan should
not blur that line even after everything above is ready.