Adds since/until date-range scoping to cluster_commit_hours() and workplan_task_counts() (threaded through calculate_target_basis()), needed whenever a candidate is one bounded workplan within a repo whose overall history spans much more (net-kingdom, railiance-apps) rather than the whole repo being the candidate (vergabe-teilnahme, info-tech-canon). Fixes a real bug found along the way: workplan_task_counts() only scanned the top level of workplans/, missing net-kingdom's workplans/archived/ convention entirely - silently reported zero finished workplans for NK-WP-0002, which lives there. Fixed to scan recursively; added a regression test. Updates all three draft pilot-candidate manifests with calculator- derived target_basis/initial_target values, replacing the hand-picked placeholders: net-kingdom-local-identity: 200,000 -> 10,000 EUR (floor + sanity warnings) railiance-vergabe-teilnahme: 3,500,000 -> 648,800 EUR (no warnings) info-tech-canon-service-surface: 2,500,000 -> 141,800 EUR (sanity warning) history/260730-EffortCalculator-CandidateApplication.md records full derivation, warnings, and the judgment calls made explicit rather than silently picked (date-scoping windows; measuring vergabe-teilnahme's own repo rather than railiance-apps' deployment-only wiring, with both figures shown). Still draft/non-binding - WP-0008-T05 unaffected. 5 new tests (20 -> now covering since/until scoping and the archived-subdirectory fix). Full suite: 84 passing offline.
9 KiB
Development Effort Calculator Applied to Real Pilot Candidates
Document status: Dated execution record, non-normative, append-only
(workplans/TREV-WP-0010-development-effort-calculator.md T03).
Not a Phase declaration. Updates draft, non-binding
examples/pilot-candidates/*/manifest.json figures from hand-picked
illustrative placeholders to calculator-derived ones — nothing here
authorizes a real Phase (workplans/TREV-WP-0008-governance-and-pilot-rollout.md
T05 still gates that).
1. Method
Ran target_revenue.effort_calculator.calculate_target_basis (WP-0010-T02)
against each candidate's real local repository, daily_rate=1000 (EUR,
consistent with the earlier hand-picked drafts and the Licensor's own
jurisdiction), tokens_in=tokens_out=0 (no get_token_summary data was
available for these repos at the time of this run — approved_direct_costs
is therefore 0 for all three, not a claim that no AI cost was actually
incurred, just that none is currently on record).
Scoping decision, made explicit per candidate: two of the four
candidates repos are the whole repo's history (the repo's entire
purpose is the candidate); two are one bounded workplan inside a much
larger, longer-lived repo, and were date-scoped accordingly (since/
until) — running whole-repo history against a single narrow workplan
would badly overstate that workplan's own effort.
| Candidate | Repo | Scope used | Why |
|---|---|---|---|
net-kingdom-local-identity |
net-kingdom |
2026-03-01 .. 2026-03-06 |
NK-WP-0002 is one bounded workplan; net-kingdom has since grown into a much larger, multi-year security platform with dozens of unrelated workplans |
railiance-vergabe-teilnahme |
vergabe-teilnahme (primary) + railiance-apps (secondary, scoped) |
whole repo (primary); 2026-05-18 .. 2026-07-12 (secondary) |
See §3 — the actual application code lives in vergabe-teilnahme, a separate repo from railiance-apps, which only holds the Helm/deployment wiring |
info-tech-canon-service-surface |
info-tech-canon |
whole repo | The candidate is the repo's cumulative service surface (ITC-WP-0001–0012); no narrower scope applies |
2. net-kingdom-local-identity
{
"estimated_effort_days": 1.0,
"daily_rate": 1000,
"approved_direct_costs": 0.0,
"warnings": [
"Raw commit-clustered estimate was 0.804 day(s), below the 1.0-day floor. Floored to 1.0 day(s)... very likely a measurement gap... manual override... recommended.",
"1 finished workplan(s) and 21 finished task(s) on record suggest more real effort than the 0.80-day raw time estimate reflects — treat the time estimate as under-counted and consider a manual override."
],
"derivation": {
"raw_commit_clustered_hours": 6.435, "sessions": 4, "commits": 19,
"finished_workplans": 1, "finished_tasks": 21,
"file_count": 274, "line_count": 44359
}
}
Both warnings fired. The raw 0.8-day estimate hit the 1-day floor
(§1's date-scoping correctly isolated NK-WP-0002's own 19 commits across
4 sessions), and the sanity-check independently flagged that 21 finished
tasks across one workplan implies more real effort than 0.8 raw days
suggests. This is exactly the situation the maintainer's requested
floor-and-warning design exists for: the manifest below uses the
1.0-day floored value, not a manually-adjusted "better" number — a human
reviewing this candidate before any real Phase declaration should treat
estimated_effort_days: 1.0 as a flagged, likely-too-low placeholder, not
a settled figure.
Manifest updated: estimated_effort_days: 1.0, approved_direct_costs: 0,
target_multiple: 10 (unchanged, Incremental) → Initial Target: 10,000 EUR
(previously a hand-picked 200,000 EUR — the calculator's own honest,
warning-flagged output is materially lower, not a refinement of the old
guess).
3. railiance-vergabe-teilnahme
Two repos exist for this candidate, discovered during the earlier
architecture work: railiance-apps holds the Helm/deployment wiring;
vergabe-teilnahme holds the actual Django application source code.
RAILIANCE-WP-0002/-0014 (the workplans naming this Milestone Release)
live in railiance-apps, but the real development effort producing the
application itself happened in vergabe-teilnahme.
Primary figure used — vergabe-teilnahme, whole-repo history (no
scoping; the repo's entire purpose is this one application):
{
"estimated_effort_days": 6.488,
"daily_rate": 1000,
"approved_direct_costs": 0.0,
"warnings": [],
"derivation": {
"raw_commit_clustered_hours": 51.904, "sessions": 42, "commits": 223,
"finished_workplans": 1, "finished_tasks": 123,
"file_count": 322, "line_count": 26773
}
}
Secondary figure, not used in the manifest — railiance-apps, date-scoped
to 2026-05-18..2026-07-12:
{
"estimated_effort_days": 4.146,
"derivation": {
"raw_commit_clustered_hours": 33.168, "sessions": 36, "commits": 127,
"finished_workplans": 12, "finished_tasks": 71,
"file_count": 140, "line_count": 11118
}
}
Judgment call, made explicit rather than silently picked: this
document uses vergabe-teilnahme's figure as the candidate's
target_basis, since that repo is where the substantive product
development happened; railiance-apps's deployment effort (4.146 days)
is real work but comparatively thin infrastructure glue, not the
Milestone Release's own value creation. A different, equally defensible
call would sum or otherwise combine both — flagged here so a human
reviewing this later can see both numbers and the reasoning, not just
the one that was picked.
Manifest updated: estimated_effort_days: 6.488,
approved_direct_costs: 0 (the hand-picked draft's 5000 placeholder
removed — no real token-cost or other direct-cost data exists yet),
target_multiple: 100 (unchanged, Product-defining) → Initial Target:
648,800 EUR (previously a hand-picked 3,500,000 EUR).
4. info-tech-canon-service-surface
{
"estimated_effort_days": 1.418,
"daily_rate": 1000,
"approved_direct_costs": 0.0,
"warnings": [
"12 finished workplan(s) and 51 finished task(s) on record suggest more real effort than the 1.42-day raw time estimate reflects — treat the time estimate as under-counted and consider a manual override."
],
"derivation": {
"raw_commit_clustered_hours": 11.348, "sessions": 12, "commits": 48,
"finished_workplans": 12, "finished_tasks": 51,
"file_count": 235, "line_count": 93663
}
}
Above the 1-day floor (no floor warning), but the sanity-check warning
still fired — 12 finished workplans and 51 finished tasks against only
1.42 raw days is a clear under-count signal in its own right, independent
of the floor. Same treatment as net-kingdom: the flagged, warning-
carrying value is used as-is, not manually adjusted.
Manifest updated: estimated_effort_days: 1.418,
approved_direct_costs: 0, target_multiple: 100 (unchanged,
Product-defining) → Initial Target: 141,800 EUR (previously a
hand-picked 2,500,000 EUR).
5. A bug found and fixed along the way
Applying the calculator to net-kingdom surfaced a real defect in
workplan_task_counts(): it originally scanned only the top level of
<repo>/workplans/, non-recursively — and NK-WP-0002 lives in
net-kingdom/workplans/archived/, a convention several repos in this
ecosystem use for finished workplans instead of deleting them. The
initial scoped run silently reported zero finished workplans/tasks for a
candidate that has exactly one, cleanly finished workplan. Fixed to scan
recursively (rglob instead of glob); a regression test
(test_workplan_task_counts_scans_archived_subdirectory) now guards this.
6. Summary table
| Candidate | Old (hand-picked) Initial Target | New (calculator-derived) Initial Target | Warnings fired |
|---|---|---|---|
net-kingdom-local-identity |
200,000 EUR | 10,000 EUR | Floor + sanity-check (both) |
railiance-vergabe-teilnahme |
3,500,000 EUR | 648,800 EUR | None |
info-tech-canon-service-surface |
2,500,000 EUR | 141,800 EUR | Sanity-check only |
Every calculator-derived figure is materially lower than the earlier
hand-picked illustrative placeholder — expected, since those placeholders
were invented for shape-checking the schema, not reasoned from any real
measurement. Two of the three carry explicit warnings recommending a
manual override before this could ever inform a real Phase declaration;
the third (vergabe-teilnahme) has no warnings, but is itself the
product of a judgment call (§3) about which of two repos to measure.
7. Non-goals
- Declaring any real Phase —
workplans/TREV-WP-0008-governance-and-pilot-rollout.mdT05 is unaffected by this document. - Resolving the