158 lines
11 KiB
Markdown
158 lines
11 KiB
Markdown
# Factory critical-path execution — 2026-09-08
|
||
|
||
Implemented and published prerequisite corrections in ops-warden, key-cape,
|
||
approval-engine and audit-core, followed by local runtime installation and an
|
||
attended OpenBao capability preflight, then verified the actual upstream issuer. The canonical integration workplan and next
|
||
admission sequence remain in
|
||
[prj-helixforge-factory](/home/worsch/prj-helixforge-factory/operations/identity-admission.md).
|
||
|
||
| Delivered | Evidence | Effect |
|
||
| --- | --- | --- |
|
||
| Warden preserves explicit policy refusal | Code `31d9b66`; 429 tests passed, four integration tests excluded by the normal suite configuration; Ruff passed. Existing SSH probe still HTTP 200/ALLOW. Installed credential request now HTTP 403 / exit 4 before transport. | Replaces misleading “unavailable / fail-open” behavior with the actual caller/owner binding refusal. WARDEN-WP-0039-T03 owns that live admission. |
|
||
| Installer refreshes the actual Warden package | `19bb75c`; initial `--force` reused a cached wheel, while `--reinstall-package ops-warden` installed the corrected source. Installed module and behavior checked. | A published fix now reaches the executing CLI. |
|
||
| KeyCape requires genuine issuer denial | `dcebd46`; complete Go suite and vet passed. Negative checks reject timeouts, server errors, invalid tokens and unrelated refusals. Image pulled by immutable digest. | Prevents false successful scope/predecessor proofs. KEY-WP-0013-T06 is done. |
|
||
| Approval audit scope is exact | Approval `b46b0f2`, Audit `bbe8c15`; 81 receiver and six sender checks passed. Exact `tenant:platform`, source approval-engine, write-only/load-bearing, explicit redact. | Resolves both tenant/redaction input waits and removes the proposed wildcard tenant scope. Credential and live admission remain open. |
|
||
| KeyCape rollout is concrete | Pinned candidate plus two credential refs, `/readyz`, and single-instance replacement passed Railiance server dry-run. Rollback restores the compatible config/image pair. | The next attended rollout starts from a reviewed patch, with known configuration and credential prerequisites. No production deployment performed. |
|
||
|
||
The human approver UI/callback is now its own KEY-WP-0013-T05 task. Its absence
|
||
does not block the independent service registrations or approval service startup.
|
||
It still blocks evidence requiring a real human approver. Together with the two
|
||
audit inputs, three source-input waits are removed from the service-startup
|
||
path; no live security gate is marked complete by that separation.
|
||
|
||
The project now records thirteen source-pinned supplying records, including
|
||
RPF-WP-0035-T05 / proposed CCR-2026-0017/0018 and WARDEN-WP-0039-T03.
|
||
The two CCRs explicitly cover verifier-side delivery only. Client-side read
|
||
lanes and linked approval audit receiver/sender custody remain distinct returns.
|
||
|
||
The immediate sequence is: ensure the now-verified upstream issuer is pinned; obtain
|
||
the named custody reviews and run the contained attended first provision;
|
||
deploy and verify KeyCape; admit audit/consumer credentials; prove deployed
|
||
approval claim/consume and native model credential delivery. Exact policy
|
||
binding and required human-approval evidence remain explicit. Runtime placement
|
||
preparation can proceed alongside this chain. The factory's exact operating
|
||
grant and enforceable budget still precede paid execution.
|
||
|
||
All four modified owner repos returned zero consistency failures. The checks
|
||
retain historical/advisory warnings where applicable; canonical reconciliation
|
||
then projected published source. Five new task assignees were empty despite
|
||
source metadata and were corrected through the supported API with readback.
|
||
HFACT-WP-0001-T02 retains that projection parity issue.
|
||
|
||
[Published evidence](/home/worsch/prj-helixforge-factory/evidence/2026-09-08-critical-path.json)
|
||
records revisions, validations and the dry-run. These changes reduce ambiguous
|
||
handoffs and unreliable checks. Time saved and autonomous throughput are not
|
||
measured. No secrets were provisioned, no new policy binding granted and no
|
||
paid model run admitted; G0–G5 remain open and the fourteen-day window has not
|
||
started.
|
||
|
||
## Runtime installation and custody authority follow-through
|
||
|
||
SAND-WP-0015-T06 is done. The existing pinned runtime is installed on
|
||
`bnt-lap001` in its owner's mode-0700 content-addressed store. The installer
|
||
checks the expected digest before writing, verifies the copied artifact,
|
||
rejects unsafe ownership/permissions and changed destinations, and publishes
|
||
atomically. Reusing an intact installation is idempotent. It is protected by
|
||
the local owner boundary; it is not root-owned or a Railiance installation.
|
||
|
||
Sand-boxer source `df5e941` passed the complete check: **188 tests and Ruff**.
|
||
The installed-path namespace smoke started Claude 2.1.263, rein and the adapter;
|
||
proved read-only runtime, private persistent HOME, isolated networking, clean
|
||
worktree and teardown. It used no model credentials or provider request.
|
||
Sand-boxer published main `3e49a98` and Glas `4499160` carry the receipt. T04 and
|
||
GLAS-WP-0012-T02 still own execution configuration, real-model acceptance and
|
||
Railiance placement. No repeat of the unchanged candidate build is needed.
|
||
|
||
RPF-WP-0035-T05 now has a successful first-provision **capability** proof.
|
||
Through the native founder-attended `openbao-platform-admin-login` envelope,
|
||
the platform diagnostic checked create/update capability on all six exact
|
||
policy, Kubernetes-role and KV data paths for CCR-2026-0017/0018. The successful
|
||
session self-revoked and removed its helper. Source `a94d06d` preserves the
|
||
metadata-only diagnostic and receipt. No secret value was read, custody seeded,
|
||
policy/role changed or production workload deployed.
|
||
|
||
The receipt preserves all attempts: the first direct launcher failed before
|
||
the child command and left revocation unconfirmed; the second native-wrapper
|
||
session revoked successfully but its query used unsupported multi-path syntax;
|
||
the final six single-path queries passed and that session revoked successfully.
|
||
The later success does not establish revocation for the first failed attempt.
|
||
|
||
The project consumes both returns in its thirteen-record dependency view.
|
||
Factory T03 and T04 remain waiting for their outstanding acceptance evidence;
|
||
installation and authority discovery no longer appear as unresolved inputs.
|
||
Source, Forgejo and the primary State Hub are reconciled at published revisions.
|
||
|
||
This removes two concrete setup uncertainties and makes installation and the
|
||
custody preflight reproducible. Throughput, hours saved and autonomous delivery
|
||
remain unmeasured. The next sequence is actual upstream signed-token issuer
|
||
proof, named CCR reviews, attended custody activation and compatible KeyCape
|
||
rollout. Separate client/audit/native credential admission, the exact factory
|
||
grant and enforceable spend limits still precede a real model run. G0–G5 and the
|
||
fourteen-day observation window remain open.
|
||
|
||
[Runtime and custody continuation receipt](2026-09-08-helixforge-factory/runtime-custody-continuation.json)
|
||
retains source revisions, validations, projection readbacks and progress IDs.
|
||
|
||
|
||
## Executable upstream issuer proof prepared
|
||
|
||
KEY-WP-0013-T07 closes the missing diagnostic preparation. KeyCape source
|
||
`6f33abd` adds a one-shot upstream verifier; source `1b9793f` pins the tested
|
||
image and [execution packet](/home/worsch/key-cape/docs/upstream-issuer-proof.md).
|
||
The probe verifies a real authorization-code response inside the adapter and
|
||
emits only a verified issuer and check metadata. It issues no downstream token.
|
||
|
||
The complete Go race suite and vet passed. Five packet/receipt tests and seven
|
||
real Traefik 3.6.7 route cases passed; ordinary callbacks remain on their normal
|
||
backend. Railiance server dry-run accepted the exact five-resource packet. The
|
||
immutable container also produced the expected one-second idle-timeout receipt
|
||
as UID 65534 with a read-only filesystem and no network.
|
||
|
||
The temporary Job has a ten-minute deadline and no retry; its route, service
|
||
and two network policies must carry the real Job UID for bounded cleanup. It
|
||
uses only the existing config YAML, without the signing-key mount or a
|
||
Kubernetes API token. That YAML contains credential data, so live execution
|
||
requires the deployment owner's admission. KEY-WP-0013-T02 retains that decision,
|
||
the actual signed issuer receipt, contained configuration pin and subsequent
|
||
custody/rollout reviews. No live issuer result is inferred from preparation.
|
||
|
||
This replaces an unspecified manual observation with a tested command and
|
||
bounded execution packet. The current receipt is
|
||
[key-cape/docs/evidence/upstream-issuer-probe.json](/home/worsch/key-cape/docs/evidence/upstream-issuer-probe.json).
|
||
|
||
|
||
## Live issuer observation completed
|
||
|
||
The user admitted the prepared ten-minute probe. At **2026-09-08 21:44:44 UTC**
|
||
it verified an actual signed upstream token with issuer exactly
|
||
**`https://auth.coulomb.social`**. Signature, audience, validity window and nonce
|
||
checks passed. The pinned container exited 0. This closes the unknown-issuer
|
||
observation in KEY-WP-0013-T02 and RPF-WP-0035-T05; the earlier preparation-only
|
||
state above is superseded by this live return.
|
||
|
||
Cleanup removed the dedicated route, Job/Pod, Service and both temporary network
|
||
policies. Deletion used the recorded object UIDs; every temporary resource is
|
||
absent. Normal KeyCape Deployment/config Secret metadata and image remained
|
||
unchanged. The probe retained no token and issued no downstream credential.
|
||
It did not prove downstream MFA/application login or activate custody.
|
||
|
||
KeyCape `41f6916` and Platform `8f40d73` published the owner returns. Project
|
||
`89041ec` consumes the live proof and records HFACT-DEC-2026-002 (Hub decision
|
||
`1c0d9fd1-4790-4d9a-be6c-0ed4c4890549`). The concrete probe approval is resolved;
|
||
its pending human-needed flag is cleared. HFACT-WP-0001-T03 remains wait for
|
||
the configuration owner to ensure `authelia.issuer` equals the verified HTTPS
|
||
value, named CCR-2026-0017/0018 reviews, and the admitted custody/compatible
|
||
KeyCape rollout. Separate client-side/audit/native delivery remains open.
|
||
|
||
The efficiency gain is one fewer unknown on the activation path and a retained
|
||
repeatable check for relevant provider/configuration changes. No renewed token
|
||
observation is needed for this unchanged proof context. Autonomous throughput,
|
||
spend and the fourteen-day factory observation are still unproved.
|
||
|
||
Final readback found stale KeyCape T02 and Platform T05 task descriptions despite
|
||
applied repository reconciliation receipts. Both were repaired from the published
|
||
source and verified. HFACT-WP-0001-T02 retains the underlying source/projection
|
||
parity work; these repairs do not establish that automatic synchronization is fixed.
|
||
|
||
[Live issuer and synchronization receipt](2026-09-08-helixforge-factory/live-upstream-issuer-continuation.json)
|
||
records the proof, cleanup, source/Hub parity and progress IDs.
|