T01: verified all five OH items still prepared in binky-control (no activity since 2026-08-08); the first-half-of-August command-day window lapsed at 0/5. Tracker now records the slip rather than carrying a stale date. OH-2026-004 prep gap closed in binky-control (92838e1) — batch is founder-blocked, not preparation-blocked. T02: gate-map G1/G8 evidence columns refreshed. T03: todo -> progress. Pre-drafted evidence/s1-decision-package.md with the decision question, three options, and an evidence table keyed to the OH ids; verdict cells fill once the batch drains. Not presented to the founder yet. Co-Authored-By: Claude Opus 5 <noreply@anthropic.com>
4.5 KiB
4.5 KiB
| id | type | repo | parent_workplan | repo_goal_id | created | reviewed |
|---|---|---|---|---|---|---|
| UPC-GATE-MAP-0001 | gate-map | prj-unattended-progress-company | UPC-WP-0001 | 79a2b057-b765-47ad-b5d9-c1bbc49eba43 | 2026-08-11 | 2026-08-12 |
Gate-to-evidence map (G1–G9)
Maps every GOAL.md success gate to owning repos, known child workplans /
queues, evidence pointers, status, and blockers. Link by ID only — task
lists live in the owning repos.
Status vocabulary: open | partial | met.
| Gate | Title | Owning repo(s) | Known child workplans / loops | Evidence path or missing | Status | Blockers |
|---|---|---|---|---|---|---|
| G1 | Administratively clean | binky-control |
BINKY-WP-0002 (done); UPC-WP-0002 (active); OH-2026-001…005; RISK-006/007; Phase 1 checklist | Tracker: evidence/g1-oh-batch.md (0/5 closed as of 2026-08-16; August command-day window lapsed — scheduling it is the blocking founder action); S1 package pre-drafted evidence/s1-decision-package.md; runbook binky-control/officehour/2026-08-command-day-runbook.md; Phase 1 + audit + CostRunRate as before — StB, DUO, HR, Qonto review, Stripe webhook still open |
partial | Orange: StB, DUO, Handelsregister, Qonto review, Stripe cleanup; Red: bank plan change, notary if purpose change |
| G2 | Company OS active | binky-control |
BINKY-WP-0001…0003 (done); OperatingRhythm; DecisionQueue; OfficeHourQueue; AutopilotWorkQueue; ControlLoopCatalog | INTENT.md v1.0 ratified DEC-2026-001; AutonomyPolicy.md; daily briefs through 2026-08-08; queues live |
partial → near met | Policy “in force” is operationally true; formal checklist still marks some governance boxes open in Reactivation Plan |
| G3 | Dogfood loop closed | binky-control, Railiance/activity-core/llm-connect |
BINKY-WP-0003…0006 (finished); REIN-A-0003 weekly review | OK-Audit v0 dogfood; rhythm on Railiance without host coding agent; ops_run ad0b05c4-… weekly review proof 2026-08-08 |
partial → strong | Need a named “S3 acceptance” evidence pack in this project; founder milestone status still ⬜ on S3 |
| G4 | Founder load within budget | binky-control (measure), this project (gate evidence) |
none dedicated | missing — no ≥30-day CEO time envelope log / KPI | open | Design + measure load; requires definition of what counts as “routine company ops” vs Red exceptions |
| G5 | External offer published | binky-control (+ website/domain as needed) |
BINKY-WP-0002-T04 (draft done); OfferCatalog flagship | OfferCatalog.md — OK Audit drafted, publishing Yellow-lane decision package not closed |
open | Yellow decision to publish; domain/website residual (AWQ-003, Reactivation digital presence) |
| G6 | First paid revenue | binky-control, finance path |
BINKY-WP-0005/0007 (Qonto read path finished) | Qonto evidence of costs/credits; Binect-related credit noted — no booked external product/service sale | open | Depends on G5 + delivery; Red for contracts/payment setup if needed |
| G7 | Repeatable path | product/service repos after first delivery | gap | missing unit economics / productized delivery after first sale | open | Premature until G5–G6; residual to durable product repos |
| G8 | Decision surface thin | binky-control |
DecisionQueue hygiene; OH batching; AutonomyPolicy lanes; UPC-WP-0002 | OH: 5 prepared (all five now with usable prepared_material — OH-2026-004 gap closed 2026-08-16), tracked in evidence/g1-oh-batch.md; surface is packaged not ad-hoc |
partial | Thinness waits on G1 OH drain (command day) |
| G9 | Residuals owned outside project | all participating repos | work-record residual convention; AWQ residual intakes | Pattern exists (e.g. AWQ residuals with origin_ref); project not complete so gate open by definition |
open | Close only at project retirement; enforce residual handoff as each UPC-WP finishes |
Cluster view (for sequencing)
| Cluster | Gates | Dominant state | Coordination home |
|---|---|---|---|
| Company vessel | G1, residual G2 | G1 blocks clean vessel | UPC-WP-0002 (active) |
| Unattended + load | G3, G4 | G3 strong; G4 missing | future UPC-WP-0003 |
| Revenue path | G5, G6, G7 | Offer drafted only | future UPC-WP-0004 |
| Governance close | G8, G9 | partial / endgame | continuous + retirement |
Update rule
When a child workplan finishes or an OH/DEC item closes, update Status and
Evidence here (or via a dated note under inventory/). Do not expand
child task prose into this map.